WWTP PIOZ

Pioz · official identifier ES8192200001010E

10,600h-e design capacity (2022) · 927th of 2,166 (tied with 1 others)

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier ES8192200001010E · reported size 10,600 h-e design capacity · received load 4,000 h-e · reported treatment: PS · data year 2022. 927th of 2,166 records with reported size in the inventory of Spain (tied with 1 others); 0.01 % of the sum of those 2,166 records in h-e (sum of records, not national capacity); nearest inventoried plant at 4.0 km · 1 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

10,600h-e design capacity
4,000h-e received load (2022)
38 %reported load/capacity ratio (not hydraulic utilisation)
927th of 2,166by reported size among the 2,166 records with a size in the inventory (tied with 1 others) · 0.01 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary (as reported to the EEA: PS) · reported levels
Nitrogen removalnot reported
Phosphorus removalyes
UV disinfectionnot reported
Statusactive
Reported coordinates40.4460, -3.1820 reported precision: approximate (~111 m) what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

REGULATORY REFERENCES

Referencia normativa: Spain

Regulatory framework of Spain · Directive (EU) 2024/3019: reported-capacity band 10,000 to 149,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

LOCATION

Castilla-La Mancha: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Pezuela de las Torres4.0 km2,000466primary and secondary
Los Santos de la Humosa10.2 km3,0001,375primary and secondary
Mondejar13.0 km9,0004,500primary and secondary
Azuqueca de Henares13.2 km65,16765,167primary, secondary and tertiary
Meco13.4 km58,68612,654primary, secondary and tertiary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP PIOZ report?

Reported size: 10,600 h-e design capacity. Received load: 4,000 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PS. Nitrogen, phosphorus and UV are shown only when explicitly reported.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.