Worldwide wastewater treatment observatory · Spain · Comunitat Valenciana

Aguas SB Observatory · public data to understand water

WWTP VALLE DEL VINALOPO

Elda · official identifier ES10030660001010E

267,200h-e design capacity (2022) · 82nd of 2,166

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier ES10030660001010E · reported size 267,200 h-e design capacity · received load 137,030 h-e · reported treatment: PST · data year 2022. 82nd of 2,166 records with reported size in the inventory of Spain; 0.26 % of the sum of those 2,166 records in h-e (sum of records, not national capacity); nearest inventoried plant at 11.4 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

267,200h-e design capacity
137,030h-e received load (2022)
51 %reported load/capacity ratio (not hydraulic utilisation)
82nd of 2,166by reported size among the 2,166 records with a size in the inventory · 0.26 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels
Nitrogen removalnot reported
Phosphorus removalyes
UV disinfectionnot reported
Statusactive
Reported coordinates38.4518, -0.8020 reported precision: reliable (<=11 m) what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

REGULATORY REFERENCES

Referencia normativa: Spain

Regulatory framework of Spain · Directive (EU) 2024/3019: reported-capacity band 150,000 p.e. or more; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

LOCATION

Comunitat Valenciana: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Salinas11.4 km7,2004,045primary, secondary and tertiary
Aspe11.5 km27,08326,487primary, secondary and tertiary
Novelda - Monforte del Cid12.3 km88,50040,068primary, secondary and tertiary
La Romana12.4 km7,5002,219primary, secondary and tertiary
Agost14.8 km11,9975,376primary, secondary and tertiary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP VALLE DEL VINALOPO report?

Reported size: 267,200 h-e design capacity. Received load: 137,030 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.