260,000h-e design capacity (2022) · 13th of 634

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier ATTP_3-449 · reported size 260,000 h-e design capacity · received load 150,937 h-e · reported treatment: PST · data year 2022. 13th of 634 records with reported size in the inventory of Austria; 1.0 % of the sum of those 634 records in h-e (sum of records, not national capacity); nearest inventoried plant at 6.9 km · 3 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

260,000h-e design capacity
150,937h-e received load (2022)
58 %reported load/capacity ratio (not hydraulic utilisation)
13th of 634by reported size among the 634 records with a size in the inventory · 1.0 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels
Nitrogen removalyes
Phosphorus removalyes
UV disinfectionnot reported
Statusactive
Reported coordinates47.8335, 16.2756 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

FUENTES PÚBLICAS

What public sources report

Documented milestones

  • 1996-10-31 · On 31 October 1996, Lower Austria authorised a 30,000 population-equivalent increase in design capacity at Wiener Neustadt-Süd wastewater treatment works. TU Wien

Other published data

Mean annual volume treated reported in the 2022 cycle10,719,854 m³/year (2022) · source

Facts taken from public documents, with their date and link; an authorisation, a project or a planned capacity do not prove operation or quantities actually treated. Aguas SB editorial layer, lot L03; it does not change the official data.

REGULATORY REFERENCES

Referencia normativa: Austria

Regulatory framework of Austria · Directive (EU) 2024/3019: reported-capacity band 150,000 p.e. or more; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

4,598,412reference kWh per year for this load
30.7kWh per h-e (average load) per year
689,762€ per year at 0.15 €/kWh
57 %share of energy used for aeration

what this estimate is · Inputs: 150,937 p.e. of reported load; equivalent average load 149,929 p.e. with the reference profile of Austria (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

11estimated hm³ of treated water per year
tertiary treatment reporteda starting point for reclamation

what this estimate is · Volume estimated from the reported load (30,187 m³/day of reference), not measured or available for reclamation.

LOCATION

Austria: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Ara Gv Abwasserbeseitigung Raum Hohe Wand - Steinfeld6.9 km32,00013,698primary, secondary and tertiary
Ara Piestingtaler Av8.0 km60,00047,027primary, secondary and tertiary
Neufeld (Neufelderseengebiet)9.7 km28,70024,062primary, secondary and tertiary
Ara Gav Ebenfurth-Pottendorf12.7 km8,5007,833primary, secondary and tertiary
Ara Gv Abwasserbeseitigung Raum Bad Vöslau15.3 km120,00075,296primary, secondary and tertiary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP ARA AWV Wr. Neustadt-Süd report?

Reported size: 260,000 h-e design capacity. Received load: 150,937 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of ARA AWV Wr. Neustadt-Süd?

Aguas SB simulator reference scenario for 150,937 p.e. of reported load: 4,598,412 kWh per year (30.7 kWh per p.e. of average load), with aeration as 57 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.