Worldwide wastewater treatment observatory · Austria

Aguas SB Observatory · public data to understand water

WWTP Gratkorn

Austria · official identifier ATTP_6-M3631054R0

533,000h-e design capacity (2022) · 5th of 634

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier ATTP_6-M3631054R0 · reported size 533,000 h-e design capacity · received load 25,000 h-e · reported treatment: PST · data year 2022. 5th of 634 records with reported size in the inventory of Austria; 2.1 % of the sum of those 634 records in h-e (sum of records, not national capacity); nearest inventoried plant at 6.0 km · 1 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

533,000h-e design capacity
25,000h-e received load (2022)
5 %reported load/capacity ratio (not hydraulic utilisation)
5th of 634by reported size among the 634 records with a size in the inventory · 2.1 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels
Nitrogen removalyes
Phosphorus removalyes
UV disinfectionnot reported
Statusactive
Reported coordinates47.1238, 15.3416 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

FUENTES PÚBLICAS

What public sources report

Documented milestones

  • 2010-06-28 · Commissioning of the third anaerobic reactor at the Gratkorn wastewater treatment plant began. University of Leoben

Other published data

Mean annual volume treated reported in the 2022 cycle1,825,000 m³/year (2022) · source

Facts taken from public documents, with their date and link; an authorisation, a project or a planned capacity do not prove operation or quantities actually treated. Aguas SB editorial layer, lot L02; it does not change the official data.

REGULATORY REFERENCES

Referencia normativa: Austria

Regulatory framework of Austria · Directive (EU) 2024/3019: reported-capacity band 150,000 p.e. or more; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

1,056,616reference kWh per year for this load
42.5kWh per h-e (average load) per year
158,492€ per year at 0.15 €/kWh
54 %share of energy used for aeration

what this estimate is · Inputs: 25,000 p.e. of reported load; equivalent average load 24,833 p.e. with the reference profile of Austria (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

1.8estimated hm³ of treated water per year
tertiary treatment reporteda starting point for reclamation

what this estimate is · Volume estimated from the reported load (5,000 m³/day of reference), not measured or available for reclamation.

LOCATION

Austria: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Deutschfeistritz-Kleinstübin6.0 km4,5003,913primary, secondary and tertiary
Hitzendorf11.1 km14,0009,158primary, secondary and tertiary
Semriach11.8 km3,0001,627primary, secondary and tertiary
Übelbach12.0 km2,6002,331primary, secondary and tertiary
St.Radegund13.1 km2,5001,594primary, secondary and tertiary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP Gratkorn report?

Reported size: 533,000 h-e design capacity. Received load: 25,000 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of Gratkorn?

Aguas SB simulator reference scenario for 25,000 p.e. of reported load: 1,056,616 kWh per year (42.5 kWh per p.e. of average load), with aeration as 54 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.