Worldwide wastewater treatment observatory · Austria

Aguas SB Observatory · public data to understand water

WWTP Welser Heide

Austria · official identifier ATTP_4-41812001

160,000h-e design capacity (2022) · 20th of 634

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier ATTP_4-41812001 · reported size 160,000 h-e design capacity · received load 149,546 h-e · reported treatment: PST · data year 2022. 20th of 634 records with reported size in the inventory of Austria; 0.62 % of the sum of those 634 records in h-e (sum of records, not national capacity); nearest inventoried plant at 4.3 km · 3 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

160,000h-e design capacity
149,546h-e received load (2022)
93 %reported load/capacity ratio (not hydraulic utilisation)
20th of 634by reported size among the 634 records with a size in the inventory · 0.62 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels
Nitrogen removalyes
Phosphorus removalyes
UV disinfectionnot reported
Statusactive
Reported coordinates48.1822, 14.1375 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

FUENTES PÚBLICAS

What public sources report

Documented milestones

  • 1996-01-01 · In 1996, the city of Wels transferred its membership and usage rights in the Welser Heide regional wastewater system. City of Wels

Other published data

Mean annual volume treated reported in the 2022 cycle9,737,114 m³/year (2022) · source

Facts taken from public documents, with their date and link; an authorisation, a project or a planned capacity do not prove operation or quantities actually treated. Aguas SB editorial layer, lot L05; it does not change the official data.

REGULATORY REFERENCES

Referencia normativa: Austria

Regulatory framework of Austria · Directive (EU) 2024/3019: reported-capacity band 150,000 p.e. or more; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

4,564,593reference kWh per year for this load
30.7kWh per h-e (average load) per year
684,689€ per year at 0.15 €/kWh
57 %share of energy used for aeration

what this estimate is · Inputs: 149,546 p.e. of reported load; equivalent average load 148,548 p.e. with the reference profile of Austria (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

10.9estimated hm³ of treated water per year
tertiary treatment reporteda starting point for reclamation

what this estimate is · Volume estimated from the reported load (29,909 m³/day of reference), not measured or available for reclamation.

LOCATION

Austria: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Allhaming4.3 km2,5001,354primary, secondary and tertiary
Unteres Kremstal7.7 km30,00022,743primary, secondary and tertiary
Sipbachzell8.2 km2,3001,725primary, secondary and tertiary
Trattnachtal14.2 km65,00052,005primary, secondary and tertiary
Ried /Traunkreis15.4 km4,0002,214primary, secondary and tertiary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP Welser Heide report?

Reported size: 160,000 h-e design capacity. Received load: 149,546 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of Welser Heide?

Aguas SB simulator reference scenario for 149,546 p.e. of reported load: 4,564,593 kWh per year (30.7 kWh per p.e. of average load), with aeration as 57 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.