Worldwide wastewater treatment observatory · Belgium

Aguas SB Observatory · public data to understand water

WWTP ORP-LE-GRAND

Belgium · official identifier BERW2512001

6,300h-e design capacity (2022) · 269th of 397 (tied with 4 others)

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier BERW2512001 · reported size 6,300 h-e design capacity · received load 1,089 h-e · reported treatment: PS · data year 2022. 269th of 397 records with reported size in the inventory of Belgium (tied with 4 others); 0.06 % of the sum of those 397 records in h-e (sum of records, not national capacity); nearest inventoried plant at 3.8 km · 9 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

6,300h-e design capacity
1,089h-e received load (2022)
17 %reported load/capacity ratio (not hydraulic utilisation)
269th of 397by reported size among the 397 records with a size in the inventory (tied with 4 others) · 0.06 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary (as reported to the EEA: PS) · reported levels
Nitrogen removalyes
Phosphorus removalyes
UV disinfectionnot reported
Statusactive
Reported coordinates50.7193, 4.9935 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

REGULATORY REFERENCES

Referencia normativa: Belgium

Regulatory framework of Belgium · Directive (EU) 2024/3019: reported-capacity band 1,000 to 9,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

64,491reference kWh per year for this load
59.3kWh per h-e (average load) per year
9,674€ per year at 0.15 €/kWh
58 %share of energy used for aeration

what this estimate is · Inputs: 1,089 p.e. of reported load; equivalent average load 1,088 p.e. with the reference profile of Belgium (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

0.1estimated hm³ of treated water per year
tertiary treatment not reportedreclamation requires additional treatment

what this estimate is · Volume estimated from the reported load (391 m³/day of reference), not measured or available for reclamation.

LOCATION

Belgium: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Wansin3.8 km5,0007,234primary and secondary
Helecine · Berw25118015.1 km6,0001,238primary and secondary
Avernas-Le-Baudouin5.9 km8,2806,492primary and secondary
Landen - Rumsdorp8.3 km11,70010,000primary, secondary and tertiary
Jodoigne8.9 km20,0005,398primary and secondary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP ORP-LE-GRAND report?

Reported size: 6,300 h-e design capacity. Received load: 1,089 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PS. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of ORP-LE-GRAND?

Aguas SB simulator reference scenario for 1,089 p.e. of reported load: 64,491 kWh per year (59.3 kWh per p.e. of average load), with aeration as 58 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.