Worldwide wastewater treatment observatory · Croatia
Aguas SB Observatory · public data to understand water
WWTP Krapina
Croatia · official identifier HRUWWTP_0004044_001
not reportedh-e design capacity (2022)
European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier HRUWWTP_0004044_001 · reported size not reported h-e design capacity · received load 6,443 h-e · data year 2022. nearest inventoried plant at 7.8 km · 2 within 10 km. Reported data with their source; estimates are not measurements of the plant.
Aguas SB does not manage this wastewater treatment plant.
WHAT THE DATA REPORT
Reported data official data · 2022
| Treatment | not reported |
|---|---|
| Nitrogen removal | not reported |
| Phosphorus removal | not reported |
| UV disinfection | not reported |
| Status | active |
| Reported coordinates | 46.1473, 15.8755 precision reported by the source: level 2 what it means |
| Source and year | European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record |
REGULATORY REFERENCES
Referencia normativa: Croatia
Regulatory framework of Croatia. Individual applicability is not determined in this profile.
SCENARIO
Reference energy scenario for this load estimate · simulator engine
what this estimate is · Inputs: 6,443 p.e. of reported load; equivalent average load 6,445 p.e. with the reference profile of Croatia (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.
Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.
WATER THAT COULD RETURN
Reuse potential
what this estimate is · Volume estimated from the reported load (1,289 m³/day of reference), not measured or available for reclamation.
NEARBY PLANTS
Nearby wastewater treatment plants
| Plant | Distance | Capacity (h-e) | Load 2022 | Treatment |
|---|---|---|---|---|
| Krapinske Toplice | 7.8 km | 3,000 | 2,547 | primary |
| Pregrada | 9.1 km | not reported | 734 | not reported |
| Lepoglava | 14.9 km | not reported | 3,950 | not reported |
| Zlatar | 16.9 km | not reported | 3,926 | not reported |
| Zabok | 17.6 km | not reported | 19,119 | not reported |
Distances are between reported coordinates; proximity does not establish a hydraulic connection.
QUESTIONS
Frequently asked questions about this plant
What capacity does WWTP Krapina report?
Reported size: not reported h-e design capacity. Received load: 6,443 h-e. Units are retained without conversion.
What treatment is reported?
Treatment not reported. Nitrogen, phosphorus and UV are shown only when explicitly reported.
How much energy would a reference plant use with the load of Krapina?
Aguas SB simulator reference scenario for 6,443 p.e. of reported load: 292,220 kWh per year (45.3 kWh per p.e. of average load), with aeration as 48 % of consumption. Estimate with the country reference profile; not a measurement of the plant.
SOURCE AND CORRECTIONS
Source
reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.