Worldwide wastewater treatment observatory · Denmark

Aguas SB Observatory · public data to understand water

WWTP Renseanlæg Lynetten

Denmark · official identifier DK1010005

1,200,000h-e design capacity (2022) · 1st of 321

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier DK1010005 · reported size 1,200,000 h-e design capacity · received load 758,657 h-e · reported treatment: PST · data year 2022. 1st of 321 records with reported size in the inventory of Denmark; 9.8 % of the sum of those 321 records in h-e (sum of records, not national capacity); nearest inventoried plant at 6.8 km · 2 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

1,200,000h-e design capacity
758,657h-e received load (2022)
63 %reported load/capacity ratio (not hydraulic utilisation)
1st of 321by reported size among the 321 records with a size in the inventory · 9.8 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels
Nitrogen removalyes
Phosphorus removalyes
UV disinfectionnot reported
Statusactive
Reported coordinates55.6964, 12.6147 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

FUENTES PÚBLICAS

What public sources report

Documented milestones

Other published data

Mean annual volume treated reported in the 2022 cycle55,997,039 m³/year (2022) · source

Facts taken from public documents, with their date and link; an authorisation, a project or a planned capacity do not prove operation or quantities actually treated. Aguas SB editorial layer, lot L02; it does not change the official data.

REGULATORY REFERENCES

Referencia normativa: Denmark

Regulatory framework of Denmark · Directive (EU) 2024/3019: reported-capacity band 150,000 p.e. or more; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

24,086,480reference kWh per year for this load
32.5kWh per h-e (average load) per year
3,612,972€ per year at 0.15 €/kWh
59 %share of energy used for aeration

what this estimate is · Inputs: 758,657 p.e. of reported load; equivalent average load 741,663 p.e. with the reference profile of Denmark (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

86.4estimated hm³ of treated water per year
tertiary treatment reporteda starting point for reclamation

what this estimate is · Volume estimated from the reported load (236,701 m³/day of reference), not measured or available for reclamation.

LOCATION

Denmark: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Tårnby6.8 km71,00038,980primary, secondary and tertiary
Renseanlæg Damhusåen9.3 km470,000282,822primary, secondary and tertiary
Dragør11.0 km22,50011,653primary, secondary and tertiary
Mølleåværket A/S12.7 km125,00099,256primary, secondary and tertiary
Spildevandscenter Avedøre14.2 km400,000264,846primary, secondary and tertiary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP Renseanlæg Lynetten report?

Reported size: 1,200,000 h-e design capacity. Received load: 758,657 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of Renseanlæg Lynetten?

Aguas SB simulator reference scenario for 758,657 p.e. of reported load: 24,086,480 kWh per year (32.5 kWh per p.e. of average load), with aeration as 59 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.