Worldwide wastewater treatment observatory · Denmark
Aguas SB Observatory · public data to understand water
WWTP Stistrup
Denmark · official identifier DK8090362
20,000h-e design capacity (2022) · 118th of 321 (tied with 4 others)
European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier DK8090362 · reported size 20,000 h-e design capacity · received load 14,072 h-e · reported treatment: PST · data year 2022. 118th of 321 records with reported size in the inventory of Denmark (tied with 4 others); 0.16 % of the sum of those 321 records in h-e (sum of records, not national capacity); nearest inventoried plant at 19.4 km. Reported data with their source; estimates are not measurements of the plant.
Aguas SB does not manage this wastewater treatment plant.
WHAT THE DATA REPORT
Reported data official data · 2022
| Treatment | primary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels |
|---|---|
| Nitrogen removal | yes |
| Phosphorus removal | yes |
| UV disinfection | not reported |
| Status | active |
| Reported coordinates | 56.7517, 9.2470 precision reported by the source: level 2 what it means |
| Source and year | European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record |
REGULATORY REFERENCES
Referencia normativa: Denmark
Regulatory framework of Denmark · Directive (EU) 2024/3019: reported-capacity band 10,000 to 149,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.
SCENARIO
Reference energy scenario for this load estimate · simulator engine
what this estimate is · Inputs: 14,072 p.e. of reported load; equivalent average load 13,755 p.e. with the reference profile of Denmark (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.
Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.
WATER THAT COULD RETURN
Reuse potential
what this estimate is · Volume estimated from the reported load (4,390 m³/day of reference), not measured or available for reclamation.
NEARBY PLANTS
Nearby wastewater treatment plants
| Plant | Distance | Capacity (h-e) | Load 2022 | Treatment |
|---|---|---|---|---|
| Aars Renseanlæg | 19.4 km | 105,000 | 35,332 | primary, secondary and tertiary |
| Harre-Vejle | 22.6 km | 17,800 | 3,923 | primary, secondary and tertiary |
| Skals | 22.9 km | 3,500 | 1,716 | primary, secondary and tertiary |
| Nørager | 24.2 km | 7,500 | 7,854 | primary, secondary and tertiary |
| Østerstrand | 24.2 km | 125,000 | 22,686 | primary, secondary and tertiary |
Distances are between reported coordinates; proximity does not establish a hydraulic connection.
QUESTIONS
Frequently asked questions about this plant
What capacity does WWTP Stistrup report?
Reported size: 20,000 h-e design capacity. Received load: 14,072 h-e. Units are retained without conversion.
What treatment is reported?
Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.
How much energy would a reference plant use with the load of Stistrup?
Aguas SB simulator reference scenario for 14,072 p.e. of reported load: 741,165 kWh per year (53.9 kWh per p.e. of average load), with aeration as 42 % of consumption. Estimate with the country reference profile; not a measurement of the plant.
SOURCE AND CORRECTIONS
Source
reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.