Worldwide wastewater treatment observatory · Finland
Aguas SB Observatory · public data to understand water
WWTP TP (846) of Tampereen kt.
Finland · official identifier FIJVP_O000000000846
330,000h-e design capacity (2022) · 3rd of 145
European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier FIJVP_O000000000846 · reported size 330,000 h-e design capacity · received load 354,000 h-e · reported treatment: PST · data year 2022. 3rd of 145 records with reported size in the inventory of Finland; 4.5 % of the sum of those 145 records in h-e (sum of records, not national capacity); nearest inventoried plant at 6.1 km · 1 within 10 km. Reported data with their source; estimates are not measurements of the plant.
Aguas SB does not manage this wastewater treatment plant.
WHAT THE DATA REPORT
Reported data official data · 2022
| Treatment | primary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels |
|---|---|
| Nitrogen removal | not reported |
| Phosphorus removal | yes |
| UV disinfection | not reported |
| Status | active |
| Reported coordinates | 61.4882, 23.7679 precision reported by the source: level 2 what it means |
| Source and year | European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record |
FUENTES PÚBLICAS
What public sources report
Documented milestones
- 1972 · The Viinikanlahti wastewater treatment plant began operating in Tampere. City of Tampere
- 2025 · By year-end, wastewater previously sent to Viinikanlahti and Rahola had been redirected to the new Sulkavuori treatment plant. City of Tampere
Other published data
| Mean annual volume treated reported in the 2022 cycle | 25,832,925 m³/year (2022) · source |
|---|
Facts taken from public documents, with their date and link; an authorisation, a project or a planned capacity do not prove operation or quantities actually treated. Aguas SB editorial layer, lot L03; it does not change the official data.
REGULATORY REFERENCES
Referencia normativa: Finland
Regulatory framework of Finland · Directive (EU) 2024/3019: reported-capacity band 150,000 p.e. or more; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.
SCENARIO
Reference energy scenario for this load estimate · simulator engine
what this estimate is · Inputs: 354,000 p.e. of reported load; equivalent average load 354,148 p.e. with the reference profile of Finland (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.
Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.
WATER THAT COULD RETURN
Reuse potential
what this estimate is · Volume estimated from the reported load (61,950 m³/day of reference), not measured or available for reclamation.
NEARBY PLANTS
Nearby wastewater treatment plants
| Plant | Distance | Capacity (h-e) | Load 2022 | Treatment |
|---|---|---|---|---|
| Tp (845) Of Tampereen Kt. | 6.1 km | 73,000 | 90,300 | primary, secondary and tertiary |
| Tp (547) Of Tampereen Kt. | 15.6 km | 43,000 | 44,500 | primary, secondary and tertiary |
| Tp (416) Of Tampereen Kt. | 17.6 km | 19,000 | 18,100 | primary, secondary and tertiary |
| Tp (548) Of Siuro | 22.0 km | 5,100 | 3,100 | primary, secondary and tertiary |
| Tp (910) Of Valkeakosken Kt. | 29.5 km | 25,700 | 30,100 | primary, secondary and tertiary |
Distances are between reported coordinates; proximity does not establish a hydraulic connection.
QUESTIONS
Frequently asked questions about this plant
What capacity does WWTP TP (846) of Tampereen kt. report?
Reported size: 330,000 h-e design capacity. Received load: 354,000 h-e. Units are retained without conversion.
What treatment is reported?
Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.
How much energy would a reference plant use with the load of TP (846) of Tampereen kt.?
Aguas SB simulator reference scenario for 354,000 p.e. of reported load: 10,046,037 kWh per year (28.4 kWh per p.e. of average load), with aeration as 64 % of consumption. Estimate with the country reference profile; not a measurement of the plant.
SOURCE AND CORRECTIONS
Source
reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.