Worldwide wastewater treatment observatory · France

Aguas SB Observatory · public data to understand water

WWTP LA CROIX-SAINT-OUEN

France · official identifier FR036033801000

125,000h-e design capacity (2022) · 113th of 4,051 (tied with 1 others)

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier FR036033801000 · reported size 125,000 h-e design capacity · received load 104,780 h-e · reported treatment: PST · data year 2022. 113th of 4,051 records with reported size in the inventory of France (tied with 1 others); 0.13 % of the sum of those 4,051 records in h-e (sum of records, not national capacity); nearest inventoried plant at 4.5 km · 8 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

125,000h-e design capacity
104,780h-e received load (2022)
84 %reported load/capacity ratio (not hydraulic utilisation)
113th of 4,051by reported size among the 4,051 records with a size in the inventory (tied with 1 others) · 0.13 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels
Nitrogen removalyes
Phosphorus removalyes
UV disinfectionnot reported
Statusactive
Reported coordinates49.3686, 2.7737 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

FUENTES PÚBLICAS

What public sources report

Documented milestones

Facts taken from public documents, with their date and link; an authorisation, a project or a planned capacity do not prove operation or quantities actually treated. Aguas SB editorial layer, lot L07; it does not change the official data.

REGULATORY REFERENCES

Referencia normativa: France

Regulatory framework of France · Directive (EU) 2024/3019: reported-capacity band 10,000 to 149,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

3,259,119reference kWh per year for this load
31.1kWh per h-e (average load) per year
488,868€ per year at 0.15 €/kWh
60 %share of energy used for aeration

what this estimate is · Inputs: 104,780 p.e. of reported load; equivalent average load 104,832 p.e. with the reference profile of France (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

5.5estimated hm³ of treated water per year
tertiary treatment reporteda starting point for reclamation

what this estimate is · Volume estimated from the reported load (15,193 m³/day of reference), not measured or available for reclamation.

LOCATION

France: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Rivecourt4.5 km5,2004,497primary, secondary and tertiary
Saintines6.5 km3,5002,206primary, secondary and tertiary
Bethisy-Saint-Pierre7.4 km6,2005,245primary, secondary and tertiary
Verberie7.7 km4,6674,702primary, secondary and tertiary
Chevrieres-27.8 km5,6503,046primary, secondary and tertiary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP LA CROIX-SAINT-OUEN report?

Reported size: 125,000 h-e design capacity. Received load: 104,780 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of LA CROIX-SAINT-OUEN?

Aguas SB simulator reference scenario for 104,780 p.e. of reported load: 3,259,119 kWh per year (31.1 kWh per p.e. of average load), with aeration as 60 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.