Worldwide wastewater treatment observatory · France
Aguas SB Observatory · public data to understand water
WWTP PORTIRAGNES
France · official identifier FR060934209002
30,000h-e design capacity (2022) · 541st of 4,051 (tied with 28 others)
European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier FR060934209002 · reported size 30,000 h-e design capacity · received load 13,560 h-e · reported treatment: PS · data year 2022. 541st of 4,051 records with reported size in the inventory of France (tied with 28 others); 0.03 % of the sum of those 4,051 records in h-e (sum of records, not national capacity); nearest inventoried plant at 3.3 km · 3 within 10 km. Reported data with their source; estimates are not measurements of the plant.
Aguas SB does not manage this wastewater treatment plant.
WHAT THE DATA REPORT
Reported data official data · 2022
| Treatment | primary + secondary (as reported to the EEA: PS) · reported levels |
|---|---|
| Nitrogen removal | not reported |
| Phosphorus removal | not reported |
| UV disinfection | not reported |
| Status | active |
| Reported coordinates | 43.2858, 3.3457 precision reported by the source: level 2 what it means |
| Source and year | European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record |
REGULATORY REFERENCES
Referencia normativa: France
Regulatory framework of France · Directive (EU) 2024/3019: reported-capacity band 10,000 to 149,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.
SCENARIO
Reference energy scenario for this load estimate · simulator engine
what this estimate is · Inputs: 13,560 p.e. of reported load; equivalent average load 13,565 p.e. with the reference profile of France (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.
Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.
WATER THAT COULD RETURN
Reuse potential
what this estimate is · Volume estimated from the reported load (1,966 m³/day of reference), not measured or available for reclamation.
NEARBY PLANTS
Nearby wastewater treatment plants
| Plant | Distance | Capacity (h-e) | Load 2022 | Treatment |
|---|---|---|---|---|
| Sérignan Valras | 3.3 km | 53,000 | 27,341 | primary and secondary |
| Agde | 9.8 km | 197,583 | 132,033 | primary and secondary |
| Beziers | 9.8 km | 219,400 | 118,274 | primary, secondary and tertiary |
| Bessan | 10.3 km | 9,500 | 6,110 | primary, secondary and tertiary |
| Vendres (Bourg Et Zac Via Europa | 10.8 km | 5,000 | 3,025 | primary, secondary and tertiary |
Distances are between reported coordinates; proximity does not establish a hydraulic connection.
QUESTIONS
Frequently asked questions about this plant
What capacity does WWTP PORTIRAGNES report?
Reported size: 30,000 h-e design capacity. Received load: 13,560 h-e. Units are retained without conversion.
What treatment is reported?
Treatment PS. Nitrogen, phosphorus and UV are shown only when explicitly reported.
How much energy would a reference plant use with the load of PORTIRAGNES?
Aguas SB simulator reference scenario for 13,560 p.e. of reported load: 539,487 kWh per year (39.8 kWh per p.e. of average load), with aeration as 54 % of consumption. Estimate with the country reference profile; not a measurement of the plant.
SOURCE AND CORRECTIONS
Source
reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.