Worldwide wastewater treatment observatory · France
Aguas SB Observatory · public data to understand water
WWTP SAINT-JOSEPH REUNION
France · official identifier FR109741200001
18,500h-e design capacity (2022) · 835th of 4,051 (tied with 1 others)
European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier FR109741200001 · reported size 18,500 h-e design capacity · received load 14,682 h-e · reported treatment: PS · data year 2022. 835th of 4,051 records with reported size in the inventory of France (tied with 1 others); 0.02 % of the sum of those 4,051 records in h-e (sum of records, not national capacity); nearest inventoried plant at 18.1 km. Reported data with their source; estimates are not measurements of the plant.
Aguas SB does not manage this wastewater treatment plant.
WHAT THE DATA REPORT
Reported data official data · 2022
| Treatment | primary + secondary (as reported to the EEA: PS) · reported levels |
|---|---|
| Nitrogen removal | not reported |
| Phosphorus removal | not reported |
| UV disinfection | not reported |
| Status | active |
| Reported coordinates | -21.3804, 55.6020 precision reported by the source: level 2 what it means |
| Source and year | European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record |
REGULATORY REFERENCES
Referencia normativa: France
Regulatory framework of France · Directive (EU) 2024/3019: reported-capacity band 10,000 to 149,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.
SCENARIO
Reference energy scenario for this load estimate · simulator engine
what this estimate is · Inputs: 14,682 p.e. of reported load; equivalent average load 14,690 p.e. with the reference profile of France (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.
Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.
WATER THAT COULD RETURN
Reuse potential
what this estimate is · Volume estimated from the reported load (2,129 m³/day of reference), not measured or available for reclamation.
NEARBY PLANTS
Nearby wastewater treatment plants
| Plant | Distance | Capacity (h-e) | Load 2022 | Treatment |
|---|---|---|---|---|
| Steu de Saint-Pierre-Pierrefonds | 18.1 km | 100,000 | 119,991 | primary, secondary and tertiary |
| Steu de L'Entre-Deux | 19.5 km | 4,500 | 6,904 | primary and secondary |
| Saint-Louis Steu Du Gol | 25.2 km | 72,000 | 52,196 | primary, secondary and tertiary |
| Steu de L'Etang-Sale | 27.2 km | 19,200 | 23,725 | primary, secondary and tertiary |
| Step Du 'Brûle Marron' | 29.1 km | 4,500 | 3,147 | primary and secondary |
Distances are between reported coordinates; proximity does not establish a hydraulic connection.
QUESTIONS
Frequently asked questions about this plant
What capacity does WWTP SAINT-JOSEPH REUNION report?
Reported size: 18,500 h-e design capacity. Received load: 14,682 h-e. Units are retained without conversion.
What treatment is reported?
Treatment PS. Nitrogen, phosphorus and UV are shown only when explicitly reported.
How much energy would a reference plant use with the load of SAINT-JOSEPH REUNION?
Aguas SB simulator reference scenario for 14,682 p.e. of reported load: 583,338 kWh per year (39.7 kWh per p.e. of average load), with aeration as 54 % of consumption. Estimate with the country reference profile; not a measurement of the plant.
SOURCE AND CORRECTIONS
Source
reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.