Worldwide wastewater treatment observatory · Germany

Aguas SB Observatory · public data to understand water

WWTP Düren

Germany · official identifier DETP_NW35

310,000h-e design capacity (2022) · 66th of 3,798

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier DETP_NW35 · reported size 310,000 h-e design capacity · received load 575,232 h-e · reported treatment: PST · data year 2022. 66th of 3,798 records with reported size in the inventory of Germany; 0.21 % of the sum of those 3,798 records in h-e (sum of records, not national capacity); nearest inventoried plant at 4.8 km · 5 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

310,000h-e design capacity
575,232h-e received load (2022)
186 %reported load/capacity ratio (not hydraulic utilisation)
66th of 3,798by reported size among the 3,798 records with a size in the inventory · 0.21 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels
Nitrogen removalyes
Phosphorus removalyes
UV disinfectionyes
Statusactive
Reported coordinates50.8408, 6.4417 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

FUENTES PÚBLICAS

What public sources report

Population of the served area (Düren): 145,661 inhabitants (2025, North Rhine-Westphalia environmental authority).

Other published data

Mean annual volume treated reported in the 2022 cycle20,432,700 m³/year (2022) · source

Facts taken from public documents, with their date and link; an authorisation, a project or a planned capacity do not prove operation or quantities actually treated. Aguas SB editorial layer, lot L03; it does not change the official data.

REGULATORY REFERENCES

Referencia normativa: Germany

Regulatory framework of Germany · Directive (EU) 2024/3019: reported-capacity band 150,000 p.e. or more; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

16,172,144reference kWh per year for this load
28.1kWh per h-e (average load) per year
2,425,822€ per year at 0.15 €/kWh
63 %share of energy used for aeration

what this estimate is · Inputs: 575,232 p.e. of reported load; equivalent average load 575,692 p.e. with the reference profile of Germany (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

45.4estimated hm³ of treated water per year
tertiary treatment reporteda starting point for reclamation

what this estimate is · Volume estimated from the reported load (124,250 m³/day of reference), not measured or available for reclamation.

LOCATION

Germany: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Krauthausen4.8 km10,0006,468primary, secondary and tertiary
Langerwehe5.5 km11,6209,980primary, secondary and tertiary
Hambach6.8 km12,00010,195primary, secondary and tertiary
Eschweiler-Weisweiler-Zka7.5 km157,70085,955primary, secondary and tertiary
Hürtgenwald-Gey9.5 km4,5003,623primary, secondary and tertiary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP Düren report?

Reported size: 310,000 h-e design capacity. Received load: 575,232 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of Düren?

Aguas SB simulator reference scenario for 575,232 p.e. of reported load: 16,172,144 kWh per year (28.1 kWh per p.e. of average load), with aeration as 63 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.