Worldwide wastewater treatment observatory · Germany
Aguas SB Observatory · public data to understand water
WWTP Mirow
Germany · official identifier DETP_MV55.44.1_wbu198
11,750h-e design capacity (2022) · 2058th of 3,798
European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier DETP_MV55.44.1_wbu198 · reported size 11,750 h-e design capacity · received load 6,202 h-e · reported treatment: PST · data year 2022. 2058th of 3,798 records with reported size in the inventory of Germany; < 0.01 % of the sum of those 3,798 records in h-e (sum of records, not national capacity); nearest inventoried plant at 9.0 km · 1 within 10 km. Reported data with their source; estimates are not measurements of the plant.
Aguas SB does not manage this wastewater treatment plant.
WHAT THE DATA REPORT
Reported data official data · 2022
| Treatment | primary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels |
|---|---|
| Nitrogen removal | yes |
| Phosphorus removal | yes |
| UV disinfection | not reported |
| Status | active |
| Reported coordinates | 53.2570, 12.8115 precision reported by the source: level 1 what it means |
| Source and year | European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record |
REGULATORY REFERENCES
Referencia normativa: Germany
Regulatory framework of Germany · Directive (EU) 2024/3019: reported-capacity band 10,000 to 149,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.
SCENARIO
Reference energy scenario for this load estimate · simulator engine
what this estimate is · Inputs: 6,202 p.e. of reported load; equivalent average load 6,209 p.e. with the reference profile of Germany (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.
Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.
WATER THAT COULD RETURN
Reuse potential
what this estimate is · Volume estimated from the reported load (1,340 m³/day of reference), not measured or available for reclamation.
NEARBY PLANTS
Nearby wastewater treatment plants
| Plant | Distance | Capacity (h-e) | Load 2022 | Treatment |
|---|---|---|---|---|
| Rechlin | 9.0 km | 5,000 | 2,716 | primary, secondary and tertiary |
| Wesenberg | 10.9 km | 7,450 | 6,959 | primary, secondary and tertiary |
| Neustrelitz | 21.5 km | 100,000 | 24,460 | primary, secondary and tertiary |
| Röbel | 21.7 km | 11,500 | 7,581 | primary, secondary and tertiary |
| Wittstock/Dosse | 25.7 km | 25,000 | 13,807 | primary, secondary and tertiary |
Distances are between reported coordinates; proximity does not establish a hydraulic connection.
QUESTIONS
Frequently asked questions about this plant
What capacity does WWTP Mirow report?
Reported size: 11,750 h-e design capacity. Received load: 6,202 h-e. Units are retained without conversion.
What treatment is reported?
Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.
How much energy would a reference plant use with the load of Mirow?
Aguas SB simulator reference scenario for 6,202 p.e. of reported load: 284,980 kWh per year (45.9 kWh per p.e. of average load), with aeration as 46 % of consumption. Estimate with the country reference profile; not a measurement of the plant.
SOURCE AND CORRECTIONS
Source
reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.