Worldwide wastewater treatment observatory · Hungary

Aguas SB Observatory · public data to understand water

WWTP Bugyi - Szennyviztisztito Telep

Hungary · official identifier HU-WWTP-AIA442

7,269h-e design capacity (2022) · 263rd of 829

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier HU-WWTP-AIA442 · reported size 7,269 h-e design capacity · received load 4,007 h-e · reported treatment: PS · data year 2022. 263rd of 829 records with reported size in the inventory of Hungary; 0.05 % of the sum of those 829 records in h-e (sum of records, not national capacity); nearest inventoried plant at 8.8 km · 1 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

7,269h-e design capacity
4,007h-e received load (2022)
55 %reported load/capacity ratio (not hydraulic utilisation)
263rd of 829by reported size among the 829 records with a size in the inventory · 0.05 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary (as reported to the EEA: PS) · reported levels
Nitrogen removalnot reported
Phosphorus removalnot reported
UV disinfectionnot reported
Statusactive
Reported coordinates47.2141, 19.1814 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

REGULATORY REFERENCES

Referencia normativa: Hungary

Regulatory framework of Hungary · Directive (EU) 2024/3019: reported-capacity band 1,000 to 9,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

154,638reference kWh per year for this load
43.5kWh per h-e (average load) per year
23,196€ per year at 0.15 €/kWh
76 %share of energy used for aeration

what this estimate is · Inputs: 4,007 p.e. of reported load; equivalent average load 3,557 p.e. with the reference profile of Hungary (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

0.1estimated hm³ of treated water per year
tertiary treatment not reportedreclamation requires additional treatment

what this estimate is · Volume estimated from the reported load (393 m³/day of reference), not measured or available for reclamation.

LOCATION

Hungary: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Alsonemedi - Szennyviztisztito Telep8.8 km7,4305,314primary, secondary and tertiary
Dabas - Szennyviztisztito Telep11.1 km13,17517,995primary and secondary
Ocsa - Szennyviztisztito Telep12.5 km14,00016,651primary, secondary and tertiary
Kiskunlachaza - Szennyviztisztito Telep12.5 km12,0007,811primary, secondary and tertiary
Dunavarsany - Szennyviztisztito Telep12.9 km35,24426,205primary and secondary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP Bugyi - Szennyviztisztito Telep report?

Reported size: 7,269 h-e design capacity. Received load: 4,007 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PS. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of Bugyi - Szennyviztisztito Telep?

Aguas SB simulator reference scenario for 4,007 p.e. of reported load: 154,638 kWh per year (43.5 kWh per p.e. of average load), with aeration as 76 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.