Worldwide wastewater treatment observatory · Hungary
Aguas SB Observatory · public data to understand water
WWTP Garab - Szennyviztisztito Telep
Hungary · official identifier HU-WWTP-AIY170
150h-e design capacity (2022) · 805th of 829 (tied with 3 others)
European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier HU-WWTP-AIY170 · reported size 150 h-e design capacity · received load 120 h-e · reported treatment: PST · data year 2022. 805th of 829 records with reported size in the inventory of Hungary (tied with 3 others); < 0.01 % of the sum of those 829 records in h-e (sum of records, not national capacity); nearest inventoried plant at 5.4 km · 8 within 10 km. Reported data with their source; estimates are not measurements of the plant.
Aguas SB does not manage this wastewater treatment plant.
WHAT THE DATA REPORT
Reported data official data · 2022
| Treatment | primary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels |
|---|---|
| Nitrogen removal | yes |
| Phosphorus removal | yes |
| UV disinfection | not reported |
| Status | active |
| Reported coordinates | 47.9789, 19.6362 precision reported by the source: level 2 what it means |
| Source and year | European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record |
REGULATORY REFERENCES
Referencia normativa: Hungary
Regulatory framework of Hungary · Directive (EU) 2024/3019: reported-capacity band under 1,000 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.
SCENARIO
Reference energy scenario for this load estimate · simulator engine
what this estimate is · Inputs: 120 p.e. of reported load; equivalent average load 109 p.e. with the reference profile of Hungary (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.
Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.
WATER THAT COULD RETURN
Reuse potential
what this estimate is · Volume estimated from the reported load (12 m³/day of reference), not measured or available for reclamation.
NEARBY PLANTS
Nearby wastewater treatment plants
| Plant | Distance | Capacity (h-e) | Load 2022 | Treatment |
|---|---|---|---|---|
| Kisbarkany - Szennyviztisztito Telep | 5.4 km | 200 | 91 | primary, secondary and tertiary |
| Nagybarkany - Szennyviztisztito Telep | 6.0 km | 525 | 483 | primary, secondary and tertiary |
| Markhaza- Szennyviztisztito Telep | 6.7 km | 200 | 263 | primary, secondary and tertiary |
| Tar - Szennyviztisztito Telep | 7.4 km | 2,660 | 2,790 | primary and secondary |
| Lucfalva - Szennyviztisztito Telep | 7.4 km | 433 | 497 | primary, secondary and tertiary |
Distances are between reported coordinates; proximity does not establish a hydraulic connection.
QUESTIONS
Frequently asked questions about this plant
What capacity does WWTP Garab - Szennyviztisztito Telep report?
Reported size: 150 h-e design capacity. Received load: 120 h-e. Units are retained without conversion.
What treatment is reported?
Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.
How much energy would a reference plant use with the load of Garab - Szennyviztisztito Telep?
Aguas SB simulator reference scenario for 120 p.e. of reported load: 10,191 kWh per year (93.8 kWh per p.e. of average load), with aeration as 46 % of consumption. Estimate with the country reference profile; not a measurement of the plant.
SOURCE AND CORRECTIONS
Source
reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.