Worldwide wastewater treatment observatory · Hungary

Aguas SB Observatory · public data to understand water

WWTP Tardos - Szennyviztisztito Telep

Hungary · official identifier HU-WWTP-AIC083

2,500h-e design capacity (2022) · 526th of 829 (tied with 4 others)

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier HU-WWTP-AIC083 · reported size 2,500 h-e design capacity · received load 2,102 h-e · reported treatment: PST · data year 2022. 526th of 829 records with reported size in the inventory of Hungary (tied with 4 others); 0.02 % of the sum of those 829 records in h-e (sum of records, not national capacity); nearest inventoried plant at 5.4 km · 4 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

2,500h-e design capacity
2,102h-e received load (2022)
84 %reported load/capacity ratio (not hydraulic utilisation)
526th of 829by reported size among the 829 records with a size in the inventory (tied with 4 others) · 0.02 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels
Nitrogen removalyes
Phosphorus removalyes
UV disinfectionnot reported
Statusactive
Reported coordinates47.6558, 18.4524 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

REGULATORY REFERENCES

Regulatory reference: Hungary

Regulatory framework of Hungary · Directive (EU) 2024/3019: reported-capacity band 1,000 to 9,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

84,120reference kWh per year for this load
45.1kWh per h-e (average load) per year
12,618€ per year at 0.15 €/kWh
73 %share of energy used for aeration

what this estimate is · Inputs: 2,102 p.e. of reported load; equivalent average load 1,864 p.e. with the reference profile of Hungary (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

0.1estimated hm³ of treated water per year
tertiary treatment reporteda starting point for reclamation

what this estimate is · Volume estimated from the reported load (206 m³/day of reference), not measured or available for reclamation.

LOCATION

Hungary: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Hereg - Szennyviztisztito Telep5.4 km408915primary, secondary and tertiary
Tarjan - Szennyviztisztito Telep7.8 km3,1702,521primary, secondary and tertiary
Tatabanya - Szennyviztisztito Telep8.4 km109,416127,930primary, secondary and tertiary
Szomod - Szennyviztisztito Telep8.7 km3,3332,394primary, secondary and tertiary
Tata - Szennyviztisztito Telep11.0 km28,98322,979primary and secondary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP Tardos - Szennyviztisztito Telep report?

Reported size: 2,500 h-e design capacity. Received load: 2,102 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of Tardos - Szennyviztisztito Telep?

Aguas SB simulator reference scenario for 2,102 p.e. of reported load: 84,120 kWh per year (45.1 kWh per p.e. of average load), with aeration as 73 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.