Worldwide wastewater treatment observatory · Iceland

Aguas SB Observatory · public data to understand water

WWTP Egilsstadavik (Egilsstadir)

Iceland · official identifier IS016-04

30,000h-e design capacity (2022) · 6th of 22

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier IS016-04 · reported size 30,000 h-e design capacity · received load 29,500 h-e · reported treatment: P · data year 2022. 6th of 22 records with reported size in the inventory of Iceland; 3.9 % of the sum of those 22 records in h-e (sum of records, not national capacity); nearest inventoried plant at 1.6 km · 4 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

30,000h-e design capacity
29,500h-e received load (2022)
98 %reported load/capacity ratio (not hydraulic utilisation)
6th of 22by reported size among the 22 records with a size in the inventory · 3.9 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimario (as reported to the EEA: P) · reported levels
Nitrogen removalnot reported
Phosphorus removalnot reported
UV disinfectionnot reported
Statusactive
Reported coordinates65.2625, -14.4172 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

REGULATORY REFERENCES

Referencia normativa: Iceland

Regulatory framework of Iceland. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

1,281,460reference kWh per year for this load
43.4kWh per h-e (average load) per year
192,219€ per year at 0.15 €/kWh
55 %share of energy used for aeration

what this estimate is · Inputs: 29,500 p.e. of reported load; equivalent average load 29,500 p.e. with the reference profile of Iceland (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

2.2estimated hm³ of treated water per year
tertiary treatment not reportedreclamation requires additional treatment

what this estimate is · Volume estimated from the reported load (5,900 m³/day of reference), not measured or available for reclamation.

LOCATION

Iceland: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Melshorn/Votihvammur (Egilsstadir)1.6 km1,000524not reported
Einbuabla (Egilsstadir)1.6 km1,000629primary, secondary and tertiary
Manatrod (Egilsstadir)1.7 km1,000488not reported
Fellabaer (Smarahvammur)2.7 km330424primary and secondary
Neskaupsstadur36.3 km3,0002,404not reported

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP Egilsstadavik (Egilsstadir) report?

Reported size: 30,000 h-e design capacity. Received load: 29,500 h-e. Units are retained without conversion.

What treatment is reported?

Treatment P. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of Egilsstadavik (Egilsstadir)?

Aguas SB simulator reference scenario for 29,500 p.e. of reported load: 1,281,460 kWh per year (43.4 kWh per p.e. of average load), with aeration as 55 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.