Worldwide wastewater treatment observatory · Italy

Aguas SB Observatory · public data to understand water

WWTP Cimitero

Italy · official identifier IT02Q170000040

1,300h-e design capacity (2022) · 3137th of 3,726 (tied with 10 others)

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier IT02Q170000040 · reported size 1,300 h-e design capacity · received load 1,300 h-e · reported treatment: PS · data year 2022. 3137th of 3,726 records with reported size in the inventory of Italy (tied with 10 others); < 0.01 % of the sum of those 3,726 records in h-e (sum of records, not national capacity); nearest inventoried plant at 0.1 km · 22 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

1,300h-e design capacity
1,300h-e received load (2022)
100 %reported load/capacity ratio (not hydraulic utilisation)
3137th of 3,726by reported size among the 3,726 records with a size in the inventory (tied with 10 others) · < 0.01 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary (as reported to the EEA: PS) · reported levels
Nitrogen removalnot reported
Phosphorus removalnot reported
UV disinfectionnot reported
Statusactive
Reported coordinates45.7402, 7.4861 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

REGULATORY REFERENCES

Referencia normativa: Italy

Regulatory framework of Italy · Directive (EU) 2024/3019: reported-capacity band 1,000 to 9,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

52,089reference kWh per year for this load
58.1kWh per h-e (average load) per year
7,813€ per year at 0.15 €/kWh
59 %share of energy used for aeration

what this estimate is · Inputs: 1,300 p.e. of reported load; equivalent average load 897 p.e. with the reference profile of Italy (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

0.1estimated hm³ of treated water per year
tertiary treatment not reportedreclamation requires additional treatment

what this estimate is · Volume estimated from the reported load (260 m³/day of reference), not measured or available for reclamation.

LOCATION

Italy: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Tillier0.1 km200200primary
Nus_breil0.6 km1,2001,200primary
Rovarey0.6 km393393primary
Cretes0.8 km5050primary
Nus_capoluogo1.1 km1,6091,609primary and secondary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP Cimitero report?

Reported size: 1,300 h-e design capacity. Received load: 1,300 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PS. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of Cimitero?

Aguas SB simulator reference scenario for 1,300 p.e. of reported load: 52,089 kWh per year (58.1 kWh per p.e. of average load), with aeration as 59 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.