WWTP DP02002801_Guidizzolo
Italy · official identifier IT03160129000722
17,500h-e design capacity (2022) · 958th of 3,726 (tied with 3 others)
European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier IT03160129000722 · reported size 17,500 h-e design capacity · received load 10,723 h-e · reported treatment: PST · data year 2022. 958th of 3,726 records with reported size in the inventory of Italy (tied with 3 others); 0.02 % of the sum of those 3,726 records in h-e (sum of records, not national capacity); nearest inventoried plant at 6.3 km · 4 within 10 km. Reported data with their source; estimates are not measurements of the plant.
Aguas SB does not manage this wastewater treatment plant.
WHAT THE DATA REPORT
Reported data official data · 2022
| Treatment | primary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels |
|---|---|
| Nitrogen removal | yes |
| Phosphorus removal | yes |
| UV disinfection | not reported |
| Status | active |
| Reported coordinates | 45.2830, 10.5908 precision reported by the source: level 2 what it means |
| Source and year | European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record |
REGULATORY REFERENCES
Referencia normativa: Italy
Regulatory framework of Italy · Directive (EU) 2024/3019: reported-capacity band 10,000 to 149,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.
SCENARIO
Reference energy scenario for this load estimate · simulator engine
what this estimate is · Inputs: 10,723 p.e. of reported load; equivalent average load 7,400 p.e. with the reference profile of Italy (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.
Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.
WATER THAT COULD RETURN
Reuse potential
what this estimate is · Volume estimated from the reported load (2,145 m³/day of reference), not measured or available for reclamation.
NEARBY PLANTS
Nearby wastewater treatment plants
| Plant | Distance | Capacity (h-e) | Load 2022 | Treatment |
|---|---|---|---|---|
| Dp02007003_volta_mantovana_zona_sud_ovest | 6.3 km | 2,500 | 2,079 | primary and secondary |
| Dp02002601_goito | 7.5 km | 8,000 | 7,952 | primary, secondary and tertiary |
| Dp02007001_volta_mantovana_zona_nord_est | 8.0 km | 2,450 | 2,349 | primary and secondary |
| Dp02005101_rodigo | 9.9 km | 2,167 | 2,046 | primary, secondary and tertiary |
| Dp02000203_asola_castelnuovo | 10.9 km | 3,500 | 3,693 | primary, secondary and tertiary |
Distances are between reported coordinates; proximity does not establish a hydraulic connection.
QUESTIONS
Frequently asked questions about this plant
What capacity does WWTP DP02002801_Guidizzolo report?
Reported size: 17,500 h-e design capacity. Received load: 10,723 h-e. Units are retained without conversion.
What treatment is reported?
Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.
How much energy would a reference plant use with the load of DP02002801_Guidizzolo?
Aguas SB simulator reference scenario for 10,723 p.e. of reported load: 387,690 kWh per year (52.4 kWh per p.e. of average load), with aeration as 42 % of consumption. Estimate with the country reference profile; not a measurement of the plant.