WWTP Montebelluna_Loc_Busta
Italy · official identifier IT05Q90000003366
600h-e design capacity (2022) · 3377th of 3,726 (tied with 25 others)
European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier IT05Q90000003366 · reported size 600 h-e design capacity · received load 559 h-e · reported treatment: PST · data year 2022. 3377th of 3,726 records with reported size in the inventory of Italy (tied with 25 others); < 0.01 % of the sum of those 3,726 records in h-e (sum of records, not national capacity); nearest inventoried plant at 2.0 km · 10 within 10 km. Reported data with their source; estimates are not measurements of the plant.
Aguas SB does not manage this wastewater treatment plant.
WHAT THE DATA REPORT
Reported data official data · 2022
| Treatment | primary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels |
|---|---|
| Nitrogen removal | yes |
| Phosphorus removal | yes |
| UV disinfection | yes |
| Status | active |
| Reported coordinates | 45.7430, 12.0100 precision reported by the source: level 0 what it means |
| Source and year | European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record |
REGULATORY REFERENCES
Referencia normativa: Italy
Regulatory framework of Italy · Directive (EU) 2024/3019: reported-capacity band under 1,000 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.
SCENARIO
Reference energy scenario for this load estimate · simulator engine
what this estimate is · Inputs: 559 p.e. of reported load; equivalent average load 386 p.e. with the reference profile of Italy (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.
Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.
WATER THAT COULD RETURN
Reuse potential
what this estimate is · Volume estimated from the reported load (112 m³/day of reference), not measured or available for reclamation.
NEARBY PLANTS
Nearby wastewater treatment plants
| Plant | Distance | Capacity (h-e) | Load 2022 | Treatment |
|---|---|---|---|---|
| Impianto_di_depurazione_di_caerano_via_vittime_del_vajont | 2.0 km | 400 | 373 | primary, secondary and tertiary |
| Montebelluna_san_gaetano | 2.8 km | 32,000 | 31,718 | primary, secondary and tertiary |
| Fitodepurazione_di_trevignano_vicolo_venezia | 4.7 km | 120 | 49 | primary and secondary |
| Fitodepurazione_di_trevignano_via_montebianco | 6.2 km | 170 | 69 | primary and secondary |
| Impianto_di_fitodepurazione_via_dei_rizzi_maser | 6.9 km | 95 | 89 | primary and secondary |
Distances are between reported coordinates; proximity does not establish a hydraulic connection.
QUESTIONS
Frequently asked questions about this plant
What capacity does WWTP Montebelluna_Loc_Busta report?
Reported size: 600 h-e design capacity. Received load: 559 h-e. Units are retained without conversion.
What treatment is reported?
Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.
How much energy would a reference plant use with the load of Montebelluna_Loc_Busta?
Aguas SB simulator reference scenario for 559 p.e. of reported load: 27,146 kWh per year (70.3 kWh per p.e. of average load), with aeration as 51 % of consumption. Estimate with the country reference profile; not a measurement of the plant.
SOURCE AND CORRECTIONS
Source
reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.