114,500h-e design capacity (2022) · 156th of 3,726

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier IT13000000000005 · reported size 114,500 h-e design capacity · received load 46,120 h-e · reported treatment: PS · data year 2022. 156th of 3,726 records with reported size in the inventory of Italy; 0.11 % of the sum of those 3,726 records in h-e (sum of records, not national capacity); nearest inventoried plant at 1.9 km · 13 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

114,500h-e design capacity
46,120h-e received load (2022)
40 %reported load/capacity ratio (not hydraulic utilisation)
156th of 3,726by reported size among the 3,726 records with a size in the inventory · 0.11 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary (as reported to the EEA: PS) · reported levels
Nitrogen removalyes
Phosphorus removalyes
UV disinfectionnot reported
Statusactive
Reported coordinates42.3832, 14.1452 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

FUENTES PÚBLICAS

What public sources report

Documented milestones

Facts taken from public documents, with their date and link; an authorisation, a project or a planned capacity do not prove operation or quantities actually treated. Aguas SB editorial layer, lot L07; it does not change the official data.

REGULATORY REFERENCES

Referencia normativa: Italy

Regulatory framework of Italy · Directive (EU) 2024/3019: reported-capacity band 10,000 to 149,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

1,557,251reference kWh per year for this load
48.9kWh per h-e (average load) per year
233,588€ per year at 0.15 €/kWh
49 %share of energy used for aeration

what this estimate is · Inputs: 46,120 p.e. of reported load; equivalent average load 31,823 p.e. with the reference profile of Italy (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

3.4estimated hm³ of treated water per year
tertiary treatment not reportedreclamation requires additional treatment

what this estimate is · Volume estimated from the reported load (9,224 m³/day of reference), not measured or available for reclamation.

LOCATION

Italy: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Bucceri1.9 km3,5003,400primary and secondary
Palumbo2.3 km3,5003,100primary and secondary
Pianella Castellana2.5 km2,0001,200primary and secondary
Fosso del Lupo4.9 km3,7503,100primary and secondary
Valle Dell'Inferno5.9 km800800primary and secondary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP San Martino report?

Reported size: 114,500 h-e design capacity. Received load: 46,120 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PS. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of San Martino?

Aguas SB simulator reference scenario for 46,120 p.e. of reported load: 1,557,251 kWh per year (48.9 kWh per p.e. of average load), with aeration as 49 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.