Worldwide wastewater treatment observatory · Italy

Aguas SB Observatory · public data to understand water

WWTP SCAFATI_IMPIANTO_COMPRENSIORALE

Italy · official identifier IT15Q90000003629

363,635h-e design capacity (2022) · 46th of 3,726

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier IT15Q90000003629 · reported size 363,635 h-e design capacity · received load 98,615 h-e · reported treatment: PST · data year 2022. 46th of 3,726 records with reported size in the inventory of Italy; 0.35 % of the sum of those 3,726 records in h-e (sum of records, not national capacity); nearest inventoried plant at 4.6 km · 2 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

363,635h-e design capacity
98,615h-e received load (2022)
27 %reported load/capacity ratio (not hydraulic utilisation)
46th of 3,726by reported size among the 3,726 records with a size in the inventory · 0.35 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels
Nitrogen removalyes
Phosphorus removalnot reported
UV disinfectionnot reported
Statusactive
Reported coordinates40.7418, 14.5267 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

FUENTES PÚBLICAS

What public sources report

Documented milestones

  • 2009 · In December 2009, the regional bulletin recorded that construction of the Sant’Antonio Abate and Scafati plant was complete and commissioning was underway. Campania Region

Facts taken from public documents, with their date and link; an authorisation, a project or a planned capacity do not prove operation or quantities actually treated. Aguas SB editorial layer, lot L06; it does not change the official data.

REGULATORY REFERENCES

Referencia normativa: Italy

Regulatory framework of Italy · Directive (EU) 2024/3019: reported-capacity band 150,000 p.e. or more; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

2,854,762reference kWh per year for this load
42.0kWh per h-e (average load) per year
428,214€ per year at 0.15 €/kWh
50 %share of energy used for aeration

what this estimate is · Inputs: 98,615 p.e. of reported load; equivalent average load 68,044 p.e. with the reference profile of Italy (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

7.2estimated hm³ of treated water per year
tertiary treatment reporteda starting point for reclamation

what this estimate is · Volume estimated from the reported load (19,723 m³/day of reference), not measured or available for reclamation.

LOCATION

Italy: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Castellammare_di_stabia_na_impianto_foce_sarno4.6 km518,000306,564primary, secondary and tertiary
Angri_impianto_comprensiorale_6.1 km472,102237,531primary, secondary and tertiary
Collettamento_residuo_agglomeratotramonti10.9 kmnot reportednot reportednot reported
Tramonti_impianto_tramonti10.9 km7,0003,712primary and secondary
Nocera_superiore_impianto_comprensiorale11.3 km303,381140,605primary, secondary and tertiary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP SCAFATI_IMPIANTO_COMPRENSIORALE report?

Reported size: 363,635 h-e design capacity. Received load: 98,615 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of SCAFATI_IMPIANTO_COMPRENSIORALE?

Aguas SB simulator reference scenario for 98,615 p.e. of reported load: 2,854,762 kWh per year (42.0 kWh per p.e. of average load), with aeration as 50 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.