Worldwide wastewater treatment observatory · Lithuania
Aguas SB Observatory · public data to understand water
WWTP Druskininku nuoteku valykla
Lithuania · official identifier LT-AG-022-WWTP-01
26,036h-e design capacity (2022) · 25th of 60
European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier LT-AG-022-WWTP-01 · reported size 26,036 h-e design capacity · received load 16,135 h-e · reported treatment: PST · data year 2022. 25th of 60 records with reported size in the inventory of Lithuania; 0.74 % of the sum of those 60 records in h-e (sum of records, not national capacity); nearest inventoried plant at 38.3 km. Reported data with their source; estimates are not measurements of the plant.
Aguas SB does not manage this wastewater treatment plant.
WHAT THE DATA REPORT
Reported data official data · 2022
| Treatment | primary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels |
|---|---|
| Nitrogen removal | yes |
| Phosphorus removal | yes |
| UV disinfection | not reported |
| Status | active |
| Reported coordinates | 54.0469, 24.0111 precision reported by the source: level 2 what it means |
| Source and year | European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record |
REGULATORY REFERENCES
Referencia normativa: Lithuania
Regulatory framework of Lithuania · Directive (EU) 2024/3019: reported-capacity band 10,000 to 149,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.
SCENARIO
Reference energy scenario for this load estimate · simulator engine
what this estimate is · Inputs: 16,135 p.e. of reported load; equivalent average load 16,105 p.e. with the reference profile of Lithuania (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.
Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.
WATER THAT COULD RETURN
Reuse potential
what this estimate is · Volume estimated from the reported load (3,001 m³/day of reference), not measured or available for reclamation.
NEARBY PLANTS
Nearby wastewater treatment plants
| Plant | Distance | Capacity (h-e) | Load 2022 | Treatment |
|---|---|---|---|---|
| Lazdiju Nuoteku Valykla | 38.3 km | 6,500 | 4,593 | primary, secondary and tertiary |
| Varenos Nuoteku Valykla | 40.1 km | 12,000 | 7,666 | primary, secondary and tertiary |
| Alytaus Nuoteku Valykla | 43.4 km | 220,000 | 95,198 | primary, secondary and tertiary |
| Birstono-Prienu Nuoteku Valykla | 64.2 km | 19,000 | 8,391 | primary, secondary and tertiary |
| Kalvariju Nuoteku Valykla | 64.8 km | 6,600 | 4,610 | primary and secondary |
Distances are between reported coordinates; proximity does not establish a hydraulic connection.
QUESTIONS
Frequently asked questions about this plant
What capacity does WWTP Druskininku nuoteku valykla report?
Reported size: 26,036 h-e design capacity. Received load: 16,135 h-e. Units are retained without conversion.
What treatment is reported?
Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.
How much energy would a reference plant use with the load of Druskininku nuoteku valykla?
Aguas SB simulator reference scenario for 16,135 p.e. of reported load: 687,463 kWh per year (42.7 kWh per p.e. of average load), with aeration as 50 % of consumption. Estimate with the country reference profile; not a measurement of the plant.
SOURCE AND CORRECTIONS
Source
reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.