Worldwide wastewater treatment observatory · Malta
Aguas SB Observatory · public data to understand water
WWTP Cumnija Urban Wastewater Treatment Plant
Malta · official identifier MTNSTP
80,000h-e design capacity (2022) · 3rd of 4
European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier MTNSTP · reported size 80,000 h-e design capacity · received load 78,412 h-e · reported treatment: PST · data year 2022. 3rd of 4 records with reported size in the inventory of Malta; 10.8 % of the sum of those 4 records in h-e (sum of records, not national capacity); nearest inventoried plant at 7.9 km · 1 within 10 km. Reported data with their source; estimates are not measurements of the plant.
Aguas SB does not manage this wastewater treatment plant.
WHAT THE DATA REPORT
Reported data official data · 2022
| Treatment | primary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels |
|---|---|
| Nitrogen removal | yes |
| Phosphorus removal | not reported |
| UV disinfection | not reported |
| Status | active |
| Reported coordinates | 35.9681, 14.3385 precision reported by the source: level 2 what it means |
| Source and year | European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record |
REGULATORY REFERENCES
Referencia normativa: Malta
Regulatory framework of Malta · Directive (EU) 2024/3019: reported-capacity band 10,000 to 149,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.
SCENARIO
Reference energy scenario for this load estimate · simulator engine
what this estimate is · Inputs: 78,412 p.e. of reported load; equivalent average load 58,462 p.e. with the reference profile of Malta (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.
Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.
WATER THAT COULD RETURN
Reuse potential
what this estimate is · Volume estimated from the reported load (8,704 m³/day of reference), not measured or available for reclamation.
NEARBY PLANTS
Nearby wastewater treatment plants
| Plant | Distance | Capacity (h-e) | Load 2022 | Treatment |
|---|---|---|---|---|
| Ras Il-Hobz Urban Wastewater Treatment Plant | 7.9 km | 46,000 | 72,517 | primary, secondary and tertiary |
| Ta' Barkat Urban Wastewater Treatment Plant | 21.8 km | 500,000 | 376,229 | primary, secondary and tertiary |
Distances are between reported coordinates; proximity does not establish a hydraulic connection.
QUESTIONS
Frequently asked questions about this plant
What capacity does WWTP Cumnija Urban Wastewater Treatment Plant report?
Reported size: 80,000 h-e design capacity. Received load: 78,412 h-e. Units are retained without conversion.
What treatment is reported?
Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.
How much energy would a reference plant use with the load of Cumnija Urban Wastewater Treatment Plant?
Aguas SB simulator reference scenario for 78,412 p.e. of reported load: 1,868,872 kWh per year (32.0 kWh per p.e. of average load), with aeration as 58 % of consumption. Estimate with the country reference profile; not a measurement of the plant.
SOURCE AND CORRECTIONS
Source
reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.