Worldwide wastewater treatment observatory · Netherlands

Aguas SB Observatory · public data to understand water

WWTP UWWTP KRALINGSEVEER

Netherlands · official identifier NL16010

219,600h-e design capacity (2022) · 19th of 315

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier NL16010 · reported size 219,600 h-e design capacity · received load 207,283 h-e · reported treatment: PST · data year 2022. 19th of 315 records with reported size in the inventory of Netherlands; 1.0 % of the sum of those 315 records in h-e (sum of records, not national capacity); nearest inventoried plant at 4.0 km · 6 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

219,600h-e design capacity
207,283h-e received load (2022)
94 %reported load/capacity ratio (not hydraulic utilisation)
19th of 315by reported size among the 315 records with a size in the inventory · 1.0 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels
Nitrogen removalyes
Phosphorus removalyes
UV disinfectionnot reported
Statusactive
Reported coordinates51.9086, 4.5420 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

FUENTES PÚBLICAS

What public sources report

Documented milestones

Other published data

Mean annual volume treated reported in the 2022 cycle28,711,496 m³/year (2022) · source

Facts taken from public documents, with their date and link; an authorisation, a project or a planned capacity do not prove operation or quantities actually treated. Aguas SB editorial layer, lot L05; it does not change the official data.

REGULATORY REFERENCES

Referencia normativa: Netherlands

Regulatory framework of Netherlands · Directive (EU) 2024/3019: reported-capacity band 150,000 p.e. or more; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

6,921,360reference kWh per year for this load
33.4kWh per h-e (average load) per year
1,038,204€ per year at 0.15 €/kWh
56 %share of energy used for aeration

what this estimate is · Inputs: 207,283 p.e. of reported load; equivalent average load 207,035 p.e. with the reference profile of Netherlands (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

20estimated hm³ of treated water per year
tertiary treatment reporteda starting point for reclamation

what this estimate is · Volume estimated from the reported load (54,723 m³/day of reference), not measured or available for reclamation.

LOCATION

Netherlands: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Uwwtp de Groote Zaag4.0 km37,89037,766primary, secondary and tertiary
Uwwtp Groenedijk4.7 km63,00038,366primary, secondary and tertiary
Uwwtp Rotterdam-Dokhaven5.5 km423,000325,083primary, secondary and tertiary
Uwwtp Ridderkerk6.7 km72,00046,400primary, secondary and tertiary
Uwwtp Barendrecht7.9 km35,41730,050primary, secondary and tertiary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP UWWTP KRALINGSEVEER report?

Reported size: 219,600 h-e design capacity. Received load: 207,283 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of UWWTP KRALINGSEVEER?

Aguas SB simulator reference scenario for 207,283 p.e. of reported load: 6,921,360 kWh per year (33.4 kWh per p.e. of average load), with aeration as 56 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.