Worldwide wastewater treatment observatory · Norway

Aguas SB Observatory · public data to understand water

WWTP Ladehammeren renseanlegg

Norway · official identifier NO5001.0210.01

122,000h-e design capacity (2022) · 15th of 340

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier NO5001.0210.01 · reported size 122,000 h-e design capacity · received load 154,636 h-e · reported treatment: P · data year 2022. 15th of 340 records with reported size in the inventory of Norway; 1.6 % of the sum of those 340 records in h-e (sum of records, not national capacity); nearest inventoried plant at 4.4 km · 1 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

122,000h-e design capacity
154,636h-e received load (2022)
127 %reported load/capacity ratio (not hydraulic utilisation)
15th of 340by reported size among the 340 records with a size in the inventory · 1.6 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimario (as reported to the EEA: P) · reported levels
Nitrogen removalnot reported
Phosphorus removalnot reported
UV disinfectionnot reported
Statusactive
Reported coordinates63.4480, 10.4257 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

FUENTES PÚBLICAS

What public sources report

Documented milestones

  • 2019-02-13 · On 13 February 2019, discharge permit 2019.0128.T was granted for the Ladehammeren sewerage district in Trondheim. County Governor of Trøndelag

Facts taken from public documents, with their date and link; an authorisation, a project or a planned capacity do not prove operation or quantities actually treated. Aguas SB editorial layer, lot L07; it does not change the official data.

REGULATORY REFERENCES

Referencia normativa: Norway

Regulatory framework of Norway. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

4,349,304reference kWh per year for this load
36.1kWh per h-e (average load) per year
652,396€ per year at 0.15 €/kWh
52 %share of energy used for aeration

what this estimate is · Inputs: 154,636 p.e. of reported load; equivalent average load 120,615 p.e. with the reference profile of Norway (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

11.3estimated hm³ of treated water per year
tertiary treatment not reportedreclamation requires additional treatment

what this estimate is · Volume estimated from the reported load (30,927 m³/day of reference), not measured or available for reclamation.

LOCATION

Norway: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Høvringen Renseanlegg4.4 km170,000239,333primary
Stjørdal Ara Renseanlegg22.9 km35,00020,912primary, secondary and tertiary
Gammelosen Renseanlegg32.3 km14,00025,600primary
Moøya Renseanlegg45.5 km5,0002,596primary, secondary and tertiary
Levanger Sentrum Havna Renseanlegg54.9 km17,70023,392primary, secondary and tertiary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP Ladehammeren renseanlegg report?

Reported size: 122,000 h-e design capacity. Received load: 154,636 h-e. Units are retained without conversion.

What treatment is reported?

Treatment P. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of Ladehammeren renseanlegg?

Aguas SB simulator reference scenario for 154,636 p.e. of reported load: 4,349,304 kWh per year (36.1 kWh per p.e. of average load), with aeration as 52 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.