Worldwide wastewater treatment observatory · Poland
Aguas SB Observatory · public data to understand water
WWTP Kramarzewo
Poland · official identifier PLWM0542
400h-e design capacity (2022) · 1629th of 1,654 (tied with 2 others)
European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier PLWM0542 · reported size 400 h-e design capacity · received load 233 h-e · reported treatment: PS · data year 2022. 1629th of 1,654 records with reported size in the inventory of Poland (tied with 2 others); < 0.01 % of the sum of those 1,654 records in h-e (sum of records, not national capacity); nearest inventoried plant at 1.8 km · 2 within 10 km. Reported data with their source; estimates are not measurements of the plant.
Aguas SB does not manage this wastewater treatment plant.
WHAT THE DATA REPORT
Reported data official data · 2022
| Treatment | primary + secondary (as reported to the EEA: PS) · reported levels |
|---|---|
| Nitrogen removal | not reported |
| Phosphorus removal | not reported |
| UV disinfection | not reported |
| Status | active |
| Reported coordinates | 53.3370, 20.1498 precision reported by the source: level 1 what it means |
| Source and year | European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record |
REGULATORY REFERENCES
Referencia normativa: Poland
Regulatory framework of Poland · Directive (EU) 2024/3019: reported-capacity band under 1,000 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.
SCENARIO
Reference energy scenario for this load estimate · simulator engine
what this estimate is · Inputs: 233 p.e. of reported load; equivalent average load 180 p.e. with the reference profile of Poland (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.
Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.
WATER THAT COULD RETURN
Reuse potential
what this estimate is · Volume estimated from the reported load (25 m³/day of reference), not measured or available for reclamation.
NEARBY PLANTS
Nearby wastewater treatment plants
| Plant | Distance | Capacity (h-e) | Load 2022 | Treatment |
|---|---|---|---|---|
| Uzdowo | 1.8 km | 4,600 | 2,627 | primary and secondary |
| Oczyszczalnia Ścieków W Wilkowie | 3.1 km | 37,450 | 14,265 | primary, secondary and tertiary |
| Oczyszczalnia Ścieków W Dąbrównie | 10.3 km | 13,900 | 2,201 | primary and secondary |
| Oczyszczalnia Rybno | 14.1 km | 7,700 | 4,380 | primary and secondary |
| Jonkowo | 16.3 km | 7,555 | 3,578 | primary and secondary |
Distances are between reported coordinates; proximity does not establish a hydraulic connection.
QUESTIONS
Frequently asked questions about this plant
What capacity does WWTP Kramarzewo report?
Reported size: 400 h-e design capacity. Received load: 233 h-e. Units are retained without conversion.
What treatment is reported?
Treatment PS. Nitrogen, phosphorus and UV are shown only when explicitly reported.
How much energy would a reference plant use with the load of Kramarzewo?
Aguas SB simulator reference scenario for 233 p.e. of reported load: 14,421 kWh per year (79.9 kWh per p.e. of average load), with aeration as 54 % of consumption. Estimate with the country reference profile; not a measurement of the plant.
SOURCE AND CORRECTIONS
Source
reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.