Worldwide wastewater treatment observatory · Poland

Aguas SB Observatory · public data to understand water

WWTP Oczyszczalnia Hołdunów

Poland · official identifier PLSL0342

8,500h-e design capacity (2022) · 800th of 1,654 (tied with 4 others)

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier PLSL0342 · reported size 8,500 h-e design capacity · received load 6,503 h-e · reported treatment: PS · data year 2022. 800th of 1,654 records with reported size in the inventory of Poland (tied with 4 others); 0.02 % of the sum of those 1,654 records in h-e (sum of records, not national capacity); nearest inventoried plant at 2.5 km · 9 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

8,500h-e design capacity
6,503h-e received load (2022)
77 %reported load/capacity ratio (not hydraulic utilisation)
800th of 1,654by reported size among the 1,654 records with a size in the inventory (tied with 4 others) · 0.02 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary (as reported to the EEA: PS) · reported levels
Nitrogen removalyes
Phosphorus removalyes
UV disinfectionnot reported
Statusactive
Reported coordinates50.1445, 19.1333 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

REGULATORY REFERENCES

Referencia normativa: Poland

Regulatory framework of Poland · Directive (EU) 2024/3019: reported-capacity band 1,000 to 9,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

206,933reference kWh per year for this load
40.8kWh per h-e (average load) per year
31,040€ per year at 0.15 €/kWh
53 %share of energy used for aeration

what this estimate is · Inputs: 6,503 p.e. of reported load; equivalent average load 5,066 p.e. with the reference profile of Poland (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

0.3estimated hm³ of treated water per year
tertiary treatment not reportedreclamation requires additional treatment

what this estimate is · Volume estimated from the reported load (702 m³/day of reference), not measured or available for reclamation.

LOCATION

Poland: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Oczyszczalnia Ziemowit2.5 km18,70011,147primary, secondary and tertiary
Imielin5.4 km8,0007,331primary and secondary
Chełm Śląski6.6 km6,0285,845primary and secondary
Solec7.1 km10,31010,310primary, secondary and tertiary
Tychy- Urbanowice8.1 km261,265167,844primary, secondary and tertiary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP Oczyszczalnia Hołdunów report?

Reported size: 8,500 h-e design capacity. Received load: 6,503 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PS. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of Oczyszczalnia Hołdunów?

Aguas SB simulator reference scenario for 6,503 p.e. of reported load: 206,933 kWh per year (40.8 kWh per p.e. of average load), with aeration as 53 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.