Worldwide wastewater treatment observatory · Poland

Aguas SB Observatory · public data to understand water

WWTP Oczyszczalnia Jurczyce

Poland · official identifier PLDO0220

34,200h-e design capacity (2022) · 306th of 1,654

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier PLDO0220 · reported size 34,200 h-e design capacity · received load 22,641 h-e · reported treatment: PST · data year 2022. 306th of 1,654 records with reported size in the inventory of Poland; 0.06 % of the sum of those 1,654 records in h-e (sum of records, not national capacity); nearest inventoried plant at 7.5 km · 1 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

34,200h-e design capacity
22,641h-e received load (2022)
66 %reported load/capacity ratio (not hydraulic utilisation)
306th of 1,654by reported size among the 1,654 records with a size in the inventory · 0.06 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels
Nitrogen removalyes
Phosphorus removalyes
UV disinfectionnot reported
Statusactive
Reported coordinates51.0427, 16.7778 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

REGULATORY REFERENCES

Referencia normativa: Poland

Regulatory framework of Poland · Directive (EU) 2024/3019: reported-capacity band 10,000 to 149,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

689,862reference kWh per year for this load
39.1kWh per h-e (average load) per year
103,479€ per year at 0.15 €/kWh
55 %share of energy used for aeration

what this estimate is · Inputs: 22,641 p.e. of reported load; equivalent average load 17,645 p.e. with the reference profile of Poland (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

0.9estimated hm³ of treated water per year
tertiary treatment reporteda starting point for reclamation

what this estimate is · Volume estimated from the reported load (2,445 m³/day of reference), not measured or available for reclamation.

LOCATION

Poland: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Piotrowice7.5 km11,0004,509primary and secondary
Oczyszczalnia Ścieków W Kobierzycach14.5 km9,6335,341primary and secondary
Sobótka15.7 km14,80010,489primary, secondary and tertiary
Pleszew16.3 km28,05023,778primary, secondary and tertiary
Wrocławska Oczyszczalnia Ścieków19.1 km1,050,000995,006primary, secondary and tertiary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP Oczyszczalnia Jurczyce report?

Reported size: 34,200 h-e design capacity. Received load: 22,641 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of Oczyszczalnia Jurczyce?

Aguas SB simulator reference scenario for 22,641 p.e. of reported load: 689,862 kWh per year (39.1 kWh per p.e. of average load), with aeration as 55 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.