Worldwide wastewater treatment observatory · Poland
Aguas SB Observatory · public data to understand water
WWTP Oczyszczalnia Ścieków Debrzno Wieś
Poland · official identifier PLPM0290
8,745h-e design capacity (2022) · 783rd of 1,654
European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier PLPM0290 · reported size 8,745 h-e design capacity · received load 10,816 h-e · reported treatment: PST · data year 2022. 783rd of 1,654 records with reported size in the inventory of Poland; 0.02 % of the sum of those 1,654 records in h-e (sum of records, not national capacity); nearest inventoried plant at 14.4 km. Reported data with their source; estimates are not measurements of the plant.
Aguas SB does not manage this wastewater treatment plant.
WHAT THE DATA REPORT
Reported data official data · 2022
| Treatment | primary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels |
|---|---|
| Nitrogen removal | yes |
| Phosphorus removal | yes |
| UV disinfection | not reported |
| Status | active |
| Reported coordinates | 53.5324, 17.2302 precision reported by the source: level 2 what it means |
| Source and year | European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record |
REGULATORY REFERENCES
Referencia normativa: Poland
Regulatory framework of Poland · Directive (EU) 2024/3019: reported-capacity band 1,000 to 9,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.
SCENARIO
Reference energy scenario for this load estimate · simulator engine
what this estimate is · Inputs: 10,816 p.e. of reported load; equivalent average load 8,429 p.e. with the reference profile of Poland (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.
Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.
WATER THAT COULD RETURN
Reuse potential
what this estimate is · Volume estimated from the reported load (1,168 m³/day of reference), not measured or available for reclamation.
NEARBY PLANTS
Nearby wastewater treatment plants
| Plant | Distance | Capacity (h-e) | Load 2022 | Treatment |
|---|---|---|---|---|
| Miejska Oczyszczalnia Ścieków · Plpm0140 | 14.4 km | 26,130 | 23,488 | primary, secondary and tertiary |
| Radawnica | 19.6 km | 4,333 | 2,292 | primary and secondary |
| Kamień Krajeński | 21.0 km | 7,154 | 4,977 | primary and secondary |
| Gminna Oczyszczalnia Ścieków · Plkp0270 | 23.1 km | 19,500 | 12,359 | primary, secondary and tertiary |
| Okonek | 24.0 km | 6,823 | 2,590 | primary and secondary |
Distances are between reported coordinates; proximity does not establish a hydraulic connection.
QUESTIONS
Frequently asked questions about this plant
What capacity does WWTP Oczyszczalnia Ścieków Debrzno Wieś report?
Reported size: 8,745 h-e design capacity. Received load: 10,816 h-e. Units are retained without conversion.
What treatment is reported?
Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.
How much energy would a reference plant use with the load of Oczyszczalnia Ścieków Debrzno Wieś?
Aguas SB simulator reference scenario for 10,816 p.e. of reported load: 335,840 kWh per year (39.8 kWh per p.e. of average load), with aeration as 54 % of consumption. Estimate with the country reference profile; not a measurement of the plant.
SOURCE AND CORRECTIONS
Source
reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.