Worldwide wastewater treatment observatory · Poland

Aguas SB Observatory · public data to understand water

WWTP Oczyszczalnia Ścieków w Otwocku

Poland · official identifier PLMZ0081

139,500h-e design capacity (2022) · 77th of 1,654

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier PLMZ0081 · reported size 139,500 h-e design capacity · received load 110,267 h-e · reported treatment: PST · data year 2022. 77th of 1,654 records with reported size in the inventory of Poland; 0.26 % of the sum of those 1,654 records in h-e (sum of records, not national capacity); nearest inventoried plant at 3.3 km · 3 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

139,500h-e design capacity
110,267h-e received load (2022)
79 %reported load/capacity ratio (not hydraulic utilisation)
77th of 1,654by reported size among the 1,654 records with a size in the inventory · 0.26 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels
Nitrogen removalyes
Phosphorus removalyes
UV disinfectionnot reported
Statusactive
Reported coordinates52.0957, 21.2369 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

FUENTES PÚBLICAS

What public sources report

Population of the served area (Otwock): 54,496 inhabitants (2024, Polish National Water Management Authority).

Documented milestones

Facts taken from public documents, with their date and link; an authorisation, a project or a planned capacity do not prove operation or quantities actually treated. Aguas SB editorial layer, lot L07; it does not change the official data.

REGULATORY REFERENCES

Referencia normativa: Poland

Regulatory framework of Poland · Directive (EU) 2024/3019: reported-capacity band 10,000 to 149,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

2,753,269reference kWh per year for this load
32.0kWh per h-e (average load) per year
412,990€ per year at 0.15 €/kWh
61 %share of energy used for aeration

what this estimate is · Inputs: 110,267 p.e. of reported load; equivalent average load 85,943 p.e. with the reference profile of Poland (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

4.3estimated hm³ of treated water per year
tertiary treatment reporteda starting point for reclamation

what this estimate is · Volume estimated from the reported load (11,909 m³/day of reference), not measured or available for reclamation.

LOCATION

Poland: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Józefów · Plmz00823.3 km18,00017,837primary, secondary and tertiary
Plmz03006.5 km30,00022,152primary, secondary and tertiary
Emów8.7 km16,0003,584primary and secondary
Moczydłów11.1 km26,40021,651primary, secondary and tertiary
Piaseczno13.5 km163,500131,725primary, secondary and tertiary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP Oczyszczalnia Ścieków w Otwocku report?

Reported size: 139,500 h-e design capacity. Received load: 110,267 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of Oczyszczalnia Ścieków w Otwocku?

Aguas SB simulator reference scenario for 110,267 p.e. of reported load: 2,753,269 kWh per year (32.0 kWh per p.e. of average load), with aeration as 61 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.