Worldwide wastewater treatment observatory · Poland

Aguas SB Observatory · public data to understand water

WWTP Oczyszczalnia Ścieków w Siedlcach

Poland · official identifier PLMZ0050

175,000h-e design capacity (2022) · 58th of 1,654

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier PLMZ0050 · reported size 175,000 h-e design capacity · received load 172,907 h-e · reported treatment: PST · data year 2022. 58th of 1,654 records with reported size in the inventory of Poland; 0.33 % of the sum of those 1,654 records in h-e (sum of records, not national capacity); nearest inventoried plant at 6.6 km · 2 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

175,000h-e design capacity
172,907h-e received load (2022)
99 %reported load/capacity ratio (not hydraulic utilisation)
58th of 1,654by reported size among the 1,654 records with a size in the inventory · 0.33 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels
Nitrogen removalyes
Phosphorus removalyes
UV disinfectionyes
Statusactive
Reported coordinates52.1886, 22.2564 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

FUENTES PÚBLICAS

What public sources report

Population of the served area (Siedlce): 88,324 inhabitants (2024, Polish Waters).

Documented milestones

  • 2024-06-14 · The national programme recorded technical acceptance of a type MO investment at the plant. Polish Waters

Other published data

Mean annual volume treated reported in the 2022 cycle6,499,000 m³/year (2022) · source

Facts taken from public documents, with their date and link; an authorisation, a project or a planned capacity do not prove operation or quantities actually treated. Aguas SB editorial layer, lot L05; it does not change the official data.

REGULATORY REFERENCES

Referencia normativa: Poland

Regulatory framework of Poland · Directive (EU) 2024/3019: reported-capacity band 150,000 p.e. or more; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

3,953,099reference kWh per year for this load
29.3kWh per h-e (average load) per year
592,965€ per year at 0.15 €/kWh
62 %share of energy used for aeration

what this estimate is · Inputs: 172,907 p.e. of reported load; equivalent average load 134,764 p.e. with the reference profile of Poland (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

6.8estimated hm³ of treated water per year
tertiary treatment reporteda starting point for reclamation

what this estimate is · Volume estimated from the reported load (18,674 m³/day of reference), not measured or available for reclamation.

LOCATION

Poland: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Żelków6.6 km1,9501,845primary and secondary
Przygody7.1 km4,8002,384primary and secondary
Skórzec12.5 km6,0005,447primary and secondary
Mokobody13.6 km3,7452,085primary and secondary
Kotuń14.2 km3,2003,967primary and secondary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP Oczyszczalnia Ścieków w Siedlcach report?

Reported size: 175,000 h-e design capacity. Received load: 172,907 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of Oczyszczalnia Ścieków w Siedlcach?

Aguas SB simulator reference scenario for 172,907 p.e. of reported load: 3,953,099 kWh per year (29.3 kWh per p.e. of average load), with aeration as 62 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.