Poland · official identifier PLPM0130N
5,750h-e design capacity (2022) · 1066th of 1,654 (tied with 1 others)
European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier PLPM0130N · reported size 5,750 h-e design capacity · received load 2,945 h-e · reported treatment: PS · data year 2022. 1066th of 1,654 records with reported size in the inventory of Poland (tied with 1 others); 0.01 % of the sum of those 1,654 records in h-e (sum of records, not national capacity); nearest inventoried plant at 13.6 km. Reported data with their source; estimates are not measurements of the plant.
Aguas SB does not manage this wastewater treatment plant.
WHAT THE DATA REPORT
Reported data official data · 2022
| Treatment | primary + secondary (as reported to the EEA: PS) · reported levels |
|---|---|
| Nitrogen removal | not reported |
| Phosphorus removal | not reported |
| UV disinfection | not reported |
| Status | active |
| Reported coordinates | 53.7491, 17.7849 precision reported by the source: level 2 what it means |
| Source and year | European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record |
REGULATORY REFERENCES
Referencia normativa: Poland
Regulatory framework of Poland · Directive (EU) 2024/3019: reported-capacity band 1,000 to 9,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.
SCENARIO
Reference energy scenario for this load estimate · simulator engine
what this estimate is · Inputs: 2,945 p.e. of reported load; equivalent average load 2,295 p.e. with the reference profile of Poland (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.
Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.
WATER THAT COULD RETURN
Reuse potential
what this estimate is · Volume estimated from the reported load (318 m³/day of reference), not measured or available for reclamation.
NEARBY PLANTS
Nearby wastewater treatment plants
| Plant | Distance | Capacity (h-e) | Load 2022 | Treatment |
|---|---|---|---|---|
| Czersk | 13.6 km | 29,667 | 19,117 | primary, secondary and tertiary |
| Oczyszczalnia Chojnice Igły | 14.3 km | 81,950 | 75,536 | primary, secondary and tertiary |
| Oczyszczalnia Ścieków W Brusach | 15.3 km | 18,200 | 14,355 | primary, secondary and tertiary |
| Oczyszczalnia Ścieków Cisewie | 20.4 km | 9,900 | 8,041 | primary and secondary |
| Oczyszczalnia Ścieków W Tucholi | 20.9 km | 35,000 | 30,983 | primary, secondary and tertiary |
Distances are between reported coordinates; proximity does not establish a hydraulic connection.
QUESTIONS
Frequently asked questions about this plant
What capacity does WWTP Rytel report?
Reported size: 5,750 h-e design capacity. Received load: 2,945 h-e. Units are retained without conversion.
What treatment is reported?
Treatment PS. Nitrogen, phosphorus and UV are shown only when explicitly reported.
How much energy would a reference plant use with the load of Rytel?
Aguas SB simulator reference scenario for 2,945 p.e. of reported load: 106,091 kWh per year (46.2 kWh per p.e. of average load), with aeration as 72 % of consumption. Estimate with the country reference profile; not a measurement of the plant.