Worldwide wastewater treatment observatory · Romania

Aguas SB Observatory · public data to understand water

WWTP RM.VALCEA

Romania · official identifier RO4VL_51

130,000h-e design capacity (2022) · 30th of 1,622 (tied with 1 others)

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier RO4VL_51 · reported size 130,000 h-e design capacity · received load 86,667 h-e · reported treatment: PST · data year 2022. 30th of 1,622 records with reported size in the inventory of Romania (tied with 1 others); 0.56 % of the sum of those 1,622 records in h-e (sum of records, not national capacity); nearest inventoried plant at 5.5 km · 2 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

130,000h-e design capacity
86,667h-e received load (2022)
67 %reported load/capacity ratio (not hydraulic utilisation)
30th of 1,622by reported size among the 1,622 records with a size in the inventory (tied with 1 others) · 0.56 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels
Nitrogen removalyes
Phosphorus removalyes
UV disinfectionnot reported
Statusactive
Reported coordinates45.0650, 24.3430 precision reported by the source: level 1 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

FUENTES PÚBLICAS

What public sources report

Documented milestones

  • 2018-07-19 · Final acceptance of the works to modernise the Râmnicu Vâlcea wastewater treatment plant took place on 19 July 2018. Municipality of Râmnicu Vâlcea

Facts taken from public documents, with their date and link; an authorisation, a project or a planned capacity do not prove operation or quantities actually treated. Aguas SB editorial layer, lot L06; it does not change the official data.

REGULATORY REFERENCES

Referencia normativa: Romania

Regulatory framework of Romania · Directive (EU) 2024/3019: reported-capacity band 10,000 to 149,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

2,008,812reference kWh per year for this load
51.4kWh per h-e (average load) per year
301,322€ per year at 0.15 €/kWh
47 %share of energy used for aeration

what this estimate is · Inputs: 86,667 p.e. of reported load; equivalent average load 39,059 p.e. with the reference profile of Romania (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

5.1estimated hm³ of treated water per year
tertiary treatment reporteda starting point for reclamation

what this estimate is · Volume estimated from the reported load (13,867 m³/day of reference), not measured or available for reclamation.

LOCATION

Romania: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Budesti5.5 km1,000338primary and secondary
Bunesti9.8 km2,50095primary and secondary
Baile Govora12.6 km4,200773primary and secondary
Nicolae Balcescu12.7 km3,00039primary and secondary
Babeni15.2 km7,500955primary and secondary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP RM.VALCEA report?

Reported size: 130,000 h-e design capacity. Received load: 86,667 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of RM.VALCEA?

Aguas SB simulator reference scenario for 86,667 p.e. of reported load: 2,008,812 kWh per year (51.4 kWh per p.e. of average load), with aeration as 47 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.