Worldwide wastewater treatment observatory · Sweden

Aguas SB Observatory · public data to understand water

WWTP BROMMA RENINGSVERK

Sweden · official identifier SE0180-50-004

400,000h-e design capacity (2022) · 5th of 434

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier SE0180-50-004 · reported size 400,000 h-e design capacity · received load 376,800 h-e · reported treatment: PS · data year 2022. 5th of 434 records with reported size in the inventory of Sweden; 2.8 % of the sum of those 434 records in h-e (sum of records, not national capacity); nearest inventoried plant at 8.1 km · 1 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

400,000h-e design capacity
376,800h-e received load (2022)
94 %reported load/capacity ratio (not hydraulic utilisation)
5th of 434by reported size among the 434 records with a size in the inventory · 2.8 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary (as reported to the EEA: PS) · reported levels
Nitrogen removalyes
Phosphorus removalyes
UV disinfectionnot reported
Statusactive
Reported coordinates59.3374, 17.9320 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

FUENTES PÚBLICAS

What public sources report

Documented milestones

  • 2014-05-26 · On 26 May 2014, Stockholm approved a project to replace the Bromma plant and convey its wastewater by tunnel to Henriksdal. City of Stockholm

Other published data

Mean annual volume treated reported in the 2022 cycle48,627,000 m³/year (2022) · source

Facts taken from public documents, with their date and link; an authorisation, a project or a planned capacity do not prove operation or quantities actually treated. Aguas SB editorial layer, lot L04; it does not change the official data.

REGULATORY REFERENCES

Referencia normativa: Sweden

Regulatory framework of Sweden · Directive (EU) 2024/3019: reported-capacity band 150,000 p.e. or more; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

11,470,890reference kWh per year for this load
30.5kWh per h-e (average load) per year
1,720,633€ per year at 0.15 €/kWh
60 %share of energy used for aeration

what this estimate is · Inputs: 376,800 p.e. of reported load; equivalent average load 376,557 p.e. with the reference profile of Sweden (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

32.6estimated hm³ of treated water per year
tertiary treatment not reportedreclamation requires additional treatment

what this estimate is · Volume estimated from the reported load (89,302 m³/day of reference), not measured or available for reclamation.

LOCATION

Sweden: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Ekebyhov, Avloppsanlaggning8.1 km25,00027,600primary and secondary
Henriksdals Reningsverk10.4 km800,0001,200,000primary and secondary
Kappalaverket17.0 km700,000701,700primary and secondary
Blynas, Avloppsanlaggning23.7 km8,0004,700primary and secondary
Margretelund, Avloppsanlaggning26.2 km40,00029,400primary and secondary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP BROMMA RENINGSVERK report?

Reported size: 400,000 h-e design capacity. Received load: 376,800 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PS. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of BROMMA RENINGSVERK?

Aguas SB simulator reference scenario for 376,800 p.e. of reported load: 11,470,890 kWh per year (30.5 kWh per p.e. of average load), with aeration as 60 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.