Worldwide wastewater treatment observatory · Switzerland
Aguas SB Observatory · public data to understand water
WWTP ARA ARBOLDSWIL
Switzerland · official identifier CH_WWTP_288100
600h-e design capacity (2022) · 602nd of 705 (tied with 8 others)
European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier CH_WWTP_288100 · reported size 600 h-e design capacity · received load 578 h-e · reported treatment: PST · data year 2022. 602nd of 705 records with reported size in the inventory of Switzerland (tied with 8 others); < 0.01 % of the sum of those 705 records in h-e (sum of records, not national capacity); nearest inventoried plant at 1.7 km · 10 within 10 km. Reported data with their source; estimates are not measurements of the plant.
Aguas SB does not manage this wastewater treatment plant.
WHAT THE DATA REPORT
Reported data official data · 2022
| Treatment | primary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels |
|---|---|
| Nitrogen removal | not reported |
| Phosphorus removal | not reported |
| UV disinfection | not reported |
| Status | active |
| Reported coordinates | 47.4142, 7.7255 precision reported by the source: level 2 what it means |
| Source and year | European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record |
REGULATORY REFERENCES
Referencia normativa: Switzerland
Regulatory framework of Switzerland. Individual applicability is not determined in this profile.
SCENARIO
Reference energy scenario for this load estimate · simulator engine
what this estimate is · Inputs: 578 p.e. of reported load; equivalent average load 653 p.e. with the reference profile of Switzerland (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.
Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.
WATER THAT COULD RETURN
Reuse potential
what this estimate is · Volume estimated from the reported load (195 m³/day of reference), not measured or available for reclamation.
NEARBY PLANTS
Nearby wastewater treatment plants
| Plant | Distance | Capacity (h-e) | Load 2022 | Treatment |
|---|---|---|---|---|
| Ara Titterten | 1.7 km | 400 | 383 | primary, secondary and tertiary |
| Ara Frenke 2 | 2.5 km | 10,200 | 6,431 | primary, secondary and tertiary |
| Ara Lampenberg | 2.9 km | 600 | 533 | primary, secondary and tertiary |
| Ara Bennwil | 4.8 km | 720 | 574 | primary, secondary and tertiary |
| Ara Bretzwil | 5.2 km | 830 | 665 | primary, secondary and tertiary |
Distances are between reported coordinates; proximity does not establish a hydraulic connection.
QUESTIONS
Frequently asked questions about this plant
What capacity does WWTP ARA ARBOLDSWIL report?
Reported size: 600 h-e design capacity. Received load: 578 h-e. Units are retained without conversion.
What treatment is reported?
Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.
How much energy would a reference plant use with the load of ARA ARBOLDSWIL?
Aguas SB simulator reference scenario for 578 p.e. of reported load: 39,961 kWh per year (61.2 kWh per p.e. of average load), with aeration as 54 % of consumption. Estimate with the country reference profile; not a measurement of the plant.
SOURCE AND CORRECTIONS
Source
reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.