WWTP BIRKENHEAD AND WALLASEY STW
United Kingdom · official identifier UKENNW_UU_TP000017
182,337h-e design capacity (2018) · 85th of 1,875
European Environment Agency — Waterbase-UWWTD, data call 2019 (v07.01) · official identifier UKENNW_UU_TP000017 · reported size 182,337 h-e design capacity · received load 182,337 h-e · reported treatment: PS · data year 2018. 85th of 1,875 records with reported size in the inventory of United Kingdom; 0.19 % of the sum of those 1,875 records in h-e (sum of records, not national capacity); nearest inventoried plant at 3.4 km · 4 within 10 km. Reported data with their source; estimates are not measurements of the plant.
Aguas SB does not manage this wastewater treatment plant.
WHAT THE DATA REPORT
Reported data official data · 2018
| Treatment | primary + secondary (as reported to the EEA: PS) · reported levels |
|---|---|
| Nitrogen removal | not reported |
| Phosphorus removal | not reported |
| UV disinfection | not reported |
| Status | active |
| Reported coordinates | 53.3980, -3.0103 precision reported by the source: level 2 what it means |
| Source and year | European Environment Agency — Waterbase-UWWTD, data call 2019 (v07.01) · dataset record |
FUENTES PÚBLICAS
What public sources report
Documented milestones
- 2001-01-09 · The environmental register records the start date of permit NW/016993399/001 for the Birkenhead wastewater plant. Environment Agency
Facts taken from public documents, with their date and link; an authorisation, a project or a planned capacity do not prove operation or quantities actually treated. Aguas SB editorial layer, lot L06; it does not change the official data.
REGULATORY REFERENCES
Referencia normativa: United Kingdom
Regulatory framework of United Kingdom. Individual applicability is not determined in this profile.
NEARBY PLANTS
Nearby wastewater treatment plants
| Plant | Distance | Capacity (h-e) | Load 2018 | Treatment |
|---|---|---|---|---|
| Liverpool (Sandon [north Liverpool Docks] ) Stw | 3.4 km | 693,484 | 645,028 | primary and secondary |
| Bromborough Stw | 4.5 km | 154,805 | 92,435 | primary and secondary |
| Hoylake (North Wirral [meols] ) Stw | 8.8 km | 84,685 | 75,118 | primary and secondary |
| North Liverpool( Fazakerley) Stw | 9.5 km | 201,093 | 166,653 | primary and secondary |
| Heswall Sewage Treatment Works Stw | 11.1 km | 9,359 | 9,359 | primary and secondary |
Distances are between reported coordinates; proximity does not establish a hydraulic connection.
QUESTIONS
Frequently asked questions about this plant
What capacity does WWTP BIRKENHEAD AND WALLASEY STW report?
Reported size: 182,337 h-e design capacity. Received load: 182,337 h-e. Units are retained without conversion.
What treatment is reported?
Treatment PS. Nitrogen, phosphorus and UV are shown only when explicitly reported.
SOURCE AND CORRECTIONS
Source
reported data · European Environment Agency — Waterbase-UWWTD, data call 2019 (v07.01) · data 2018 · edition 2019 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.