WWTP LUTON STW
United Kingdom · official identifier UKENTH_TWU_TP000103
167,513h-e design capacity (2018) · 94th of 1,875
European Environment Agency — Waterbase-UWWTD, data call 2019 (v07.01) · official identifier UKENTH_TWU_TP000103 · reported size 167,513 h-e design capacity · received load 167,513 h-e · reported treatment: PS · data year 2018. 94th of 1,875 records with reported size in the inventory of United Kingdom; 0.18 % of the sum of those 1,875 records in h-e (sum of records, not national capacity); nearest inventoried plant at 4.2 km · 4 within 10 km. Reported data with their source; estimates are not measurements of the plant.
Aguas SB does not manage this wastewater treatment plant.
WHAT THE DATA REPORT
Reported data official data · 2018
| Treatment | primary + secondary (as reported to the EEA: PS) · reported levels |
|---|---|
| Nitrogen removal | not reported |
| Phosphorus removal | yes |
| UV disinfection | not reported |
| Status | active |
| Reported coordinates | 51.8479, -0.3704 precision reported by the source: level 2 what it means |
| Source and year | European Environment Agency — Waterbase-UWWTD, data call 2019 (v07.01) · dataset record |
FUENTES PÚBLICAS
What public sources report
Documented milestones
- 1989-12-15 · The environmental register records the start of discharge permit TH/CNTD.0084/001 for the wastewater treatment plant. Environment Agency
Facts taken from public documents, with their date and link; an authorisation, a project or a planned capacity do not prove operation or quantities actually treated. Aguas SB editorial layer, lot L05; it does not change the official data.
REGULATORY REFERENCES
Referencia normativa: United Kingdom
Regulatory framework of United Kingdom. Individual applicability is not determined in this profile.
NEARBY PLANTS
Nearby wastewater treatment plants
| Plant | Distance | Capacity (h-e) | Load 2018 | Treatment |
|---|---|---|---|---|
| Harpenden, Harpenden, Herts Stw" | 4.2 km | 38,540 | 38,540 | primary and secondary |
| Caddington Stw | 4.8 km | 6,355 | 6,355 | primary and secondary |
| Markyate, Markyate, Herts Stw" | 5.4 km | 6,155 | 6,155 | primary and secondary |
| Kimpton Stw | 6.7 km | 2,303 | 2,303 | primary and secondary |
| Ashbrook Stw | 12.6 km | 3,837 | 3,535 | primary and secondary |
Distances are between reported coordinates; proximity does not establish a hydraulic connection.
QUESTIONS
Frequently asked questions about this plant
What capacity does WWTP LUTON STW report?
Reported size: 167,513 h-e design capacity. Received load: 167,513 h-e. Units are retained without conversion.
What treatment is reported?
Treatment PS. Nitrogen, phosphorus and UV are shown only when explicitly reported.
SOURCE AND CORRECTIONS
Source