Worldwide wastewater treatment observatory · Belgium
Aguas SB Observatory · public data to understand water
WWTP ATHUS
Belgium · official identifier BERW8100401
15,750h-e design capacity (2022) · 152nd of 397 (tied with 1 others)
European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier BERW8100401 · reported size 15,750 h-e design capacity · received load 14,563 h-e · reported treatment: PS · data year 2022. 152nd of 397 records with reported size in the inventory of Belgium (tied with 1 others); 0.15 % of the sum of those 397 records in h-e (sum of records, not national capacity); nearest inventoried plant at 2.0 km · 4 within 10 km. Reported data with their source; estimates are not measurements of the plant.
Aguas SB does not manage this wastewater treatment plant.
WHAT THE DATA REPORT
Reported data official data · 2022
| Treatment | primary + secondary (as reported to the EEA: PS) · reported levels |
|---|---|
| Nitrogen removal | yes |
| Phosphorus removal | yes |
| UV disinfection | not reported |
| Status | active |
| Reported coordinates | 49.5583, 5.8398 precision reported by the source: level 2 what it means |
| Source and year | European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record |
REGULATORY REFERENCES
Referencia normativa: Belgium
Regulatory framework of Belgium · Directive (EU) 2024/3019: reported-capacity band 10,000 to 149,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.
SCENARIO
Reference energy scenario for this load estimate · simulator engine
what this estimate is · Inputs: 14,563 p.e. of reported load; equivalent average load 14,551 p.e. with the reference profile of Belgium (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.
Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.
WATER THAT COULD RETURN
Reuse potential
what this estimate is · Volume estimated from the reported load (5,228 m³/day of reference), not measured or available for reclamation.
NEARBY PLANTS
Nearby wastewater treatment plants
| Plant | Distance | Capacity (h-e) | Load 2022 | Treatment |
|---|---|---|---|---|
| Aubange · Berw8100402 | 2.0 km | 5,400 | 8,452 | primary and secondary |
| Musson · Berw8502601 | 11.8 km | 5,670 | 6,305 | primary and secondary |
| Waltzing | 13.8 km | 1,620 | 3,814 | primary and secondary |
| Arlon · Berw8100101 | 16.0 km | 31,500 | 28,417 | primary and secondary |
| Habay-la-Neuve | 24.4 km | 2,520 | 604 | primary and secondary |
Distances are between reported coordinates; proximity does not establish a hydraulic connection.
QUESTIONS
Frequently asked questions about this plant
What capacity does WWTP ATHUS report?
Reported size: 15,750 h-e design capacity. Received load: 14,563 h-e. Units are retained without conversion.
What treatment is reported?
Treatment PS. Nitrogen, phosphorus and UV are shown only when explicitly reported.
How much energy would a reference plant use with the load of ATHUS?
Aguas SB simulator reference scenario for 14,563 p.e. of reported load: 815,286 kWh per year (56.0 kWh per p.e. of average load), with aeration as 39 % of consumption. Estimate with the country reference profile; not a measurement of the plant.
SOURCE AND CORRECTIONS
Source
reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.