WWTP Afonsoeiro

Portugal · official identifier PT20915460

47,940h-e design capacity (2022) · 76th of 527

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier PT20915460 · reported size 47,940 h-e design capacity · received load 47,900 h-e · reported treatment: PST · data year 2022. 76th of 527 records with reported size in the inventory of Portugal; 0.28 % of the sum of those 527 records in h-e (sum of records, not national capacity); nearest inventoried plant at 3.4 km · 4 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

47,940h-e design capacity
47,900h-e received load (2022)
100 %reported load/capacity ratio (not hydraulic utilisation)
76th of 527by reported size among the 527 records with a size in the inventory · 0.28 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary + tertiary (more stringent) (as reported to the EEA: PST) · reported levels
Nitrogen removalyes
Phosphorus removalyes
UV disinfectionyes
Statusactive
Reported coordinates38.6961, -8.9624 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

REGULATORY REFERENCES

Referencia normativa: Portugal

Regulatory framework of Portugal · Directive (EU) 2024/3019: reported-capacity band 10,000 to 149,999 p.e.; obligations are set by agglomeration load, not by the capacity of this plant. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

1,895,448reference kWh per year for this load
39.6kWh per h-e (average load) per year
284,317€ per year at 0.15 €/kWh
56 %share of energy used for aeration

what this estimate is · Inputs: 47,900 p.e. of reported load; equivalent average load 47,900 p.e. with the reference profile of Portugal (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

3.5estimated hm³ of treated water per year
tertiary treatment reporteda starting point for reclamation

what this estimate is · Volume estimated from the reported load (9,580 m³/day of reference), not measured or available for reclamation.

LOCATION

Portugal: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Seixalinho3.4 km48,00042,350primary, secondary and tertiary
Alcochete5.0 km27,75018,000primary, secondary and tertiary
Barreiro/Moita7.6 km294,650170,000primary, secondary and tertiary
Pinhal Novo8.8 km24,00024,000primary, secondary and tertiary
Lagoinha10.7 km30,60020,500primary, secondary and tertiary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP Afonsoeiro report?

Reported size: 47,940 h-e design capacity. Received load: 47,900 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PST. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of Afonsoeiro?

Aguas SB simulator reference scenario for 47,900 p.e. of reported load: 1,895,448 kWh per year (39.6 kWh per p.e. of average load), with aeration as 56 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.