Worldwide wastewater treatment observatory · Switzerland

Aguas SB Observatory · public data to understand water

WWTP SATIGNY/BOIS-DE-BAY

Switzerland · official identifier CH_WWTP_663801

130,000h-e design capacity (2022) · 21st of 705

European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · official identifier CH_WWTP_663801 · reported size 130,000 h-e design capacity · received load 112,703 h-e · reported treatment: PS · data year 2022. 21st of 705 records with reported size in the inventory of Switzerland; 0.79 % of the sum of those 705 records in h-e (sum of records, not national capacity); nearest inventoried plant at 3.0 km · 4 within 10 km. Reported data with their source; estimates are not measurements of the plant.

Aguas SB does not manage this wastewater treatment plant.

WHAT THE DATA REPORT

Reported data official data · 2022

130,000h-e design capacity
112,703h-e received load (2022)
87 %reported load/capacity ratio (not hydraulic utilisation)
21st of 705by reported size among the 705 records with a size in the inventory · 0.79 % of the sum of those records (sum of records, not national capacity) · the largest plants in the country · how it is calculated
Treatmentprimary + secondary (as reported to the EEA: PS) · reported levels
Nitrogen removalnot reported
Phosphorus removalnot reported
UV disinfectionnot reported
Statusactive
Reported coordinates46.1985, 6.0408 precision reported by the source: level 2 what it means
Source and yearEuropean Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · dataset record

FUENTES PÚBLICAS

What public sources report

Documented milestones

  • 2009-04 · The Bois-de-Bay wastewater treatment plant in the Canton of Geneva entered service in April 2009. Canton of Geneva

Facts taken from public documents, with their date and link; an authorisation, a project or a planned capacity do not prove operation or quantities actually treated. Aguas SB editorial layer, lot L06; it does not change the official data.

REGULATORY REFERENCES

Referencia normativa: Switzerland

Regulatory framework of Switzerland. Individual applicability is not determined in this profile.

SCENARIO

Reference energy scenario for this load estimate · simulator engine

4,616,312reference kWh per year for this load
36.3kWh per h-e (average load) per year
692,447€ per year at 0.15 €/kWh
49 %share of energy used for aeration

what this estimate is · Inputs: 112,703 p.e. of reported load; equivalent average load 127,236 p.e. with the reference profile of Switzerland (hypothesis with reported load and reference profile; not a measurement). Open this scenario in the simulator · how it is calculated and what it is not.

Reference scenario computed on the server from the reported load and the country profile; an estimate, not a measurement. The simulator recomputes it when opened.

WATER THAT COULD RETURN

Reuse potential

13.9estimated hm³ of treated water per year
tertiary treatment not reportedreclamation requires additional treatment

what this estimate is · Volume estimated from the reported load (37,981 m³/day of reference), not measured or available for reclamation.

LOCATION

Switzerland: this plant on the map

this plant on the map · regional directory.

NEARBY PLANTS

Nearby wastewater treatment plants

PlantDistanceCapacity (h-e)Load 2022Treatment
Vernier-Ouest(Givaudan)3.0 km97,67675,679primary and secondary
Dardagny(Firmenich1)3.5 km47,00028,244primary and secondary
Vernier/Aire3.8 km600,000536,179primary and secondary
Chancy8.3 km13,6008,640primary and secondary
Thonex/Villette11.3 km50,00043,551primary and secondary

Distances are between reported coordinates; proximity does not establish a hydraulic connection.

QUESTIONS

Frequently asked questions about this plant

What capacity does WWTP SATIGNY/BOIS-DE-BAY report?

Reported size: 130,000 h-e design capacity. Received load: 112,703 h-e. Units are retained without conversion.

What treatment is reported?

Treatment PS. Nitrogen, phosphorus and UV are shown only when explicitly reported.

How much energy would a reference plant use with the load of SATIGNY/BOIS-DE-BAY?

Aguas SB simulator reference scenario for 112,703 p.e. of reported load: 4,616,312 kWh per year (36.3 kWh per p.e. of average load), with aeration as 49 % of consumption. Estimate with the country reference profile; not a measurement of the plant.

SOURCE AND CORRECTIONS

Source

reported data · European Environment Agency — Waterbase-UWWTD, data call 2023 (versión final pública) · data 2022 · edition 2023 · source licence: CC BY 4.0 · JSON for this plant · suggest a correction · catalogue 2026-11-06. Reported data, not a current inspection; no compliance judgements.